Aug 10 (Reuters) - Enbridge Energy Partners LP:
* U.S. pipeline and hazardous material safety administration disapproves
restart plan submitted by Enbridge Energy Partners LP over michigan
oil pipeline failure and spill
* Phmsa says plan does not contain sufficient technical details or adequate
steps to conclude that no immediate threats are elsewhere on the line that
require repair prior to any restart
* Phmsa says will not approve any restart plan that does not include excavating
and exposing additional pipe, and repairing or replacing additional pipe as
necessary
((New York Equities Desk; tel: +1 646 223 6000))
(For more news about Enbridge Energy Partners LP click here:) COPYRIGHT Copyright Thomson Reuters 2010. All rights reserved. The copying, republication or redistribution of Reuters News Content, including by framing or similar means, is expressly prohibited without the prior written consent of Thomson Reuters.
* U.S. pipeline and hazardous material safety administration disapproves
restart plan submitted by Enbridge Energy Partners LP over michigan
oil pipeline failure and spill
* Phmsa says plan does not contain sufficient technical details or adequate
steps to conclude that no immediate threats are elsewhere on the line that
require repair prior to any restart
* Phmsa says will not approve any restart plan that does not include excavating
and exposing additional pipe, and repairing or replacing additional pipe as
necessary
((New York Equities Desk; tel: +1 646 223 6000))
(For more news about Enbridge Energy Partners LP click here:) COPYRIGHT Copyright Thomson Reuters 2010. All rights reserved. The copying, republication or redistribution of Reuters News Content, including by framing or similar means, is expressly prohibited without the prior written consent of Thomson Reuters.
© 2010 AFX News