WKN: A3ECU9 | ISIN: KYG114481008 | Ticker-Symbol: R1T
Tradegate
25.08.26 | 21:46
9,570 Euro
-1,08 % -0,104
Branche
Software
Aktienmarkt
ASIEN
1-Jahres-Chart
BITDEER TECHNOLOGIES GROUP Chart 1 Jahr
5-Tage-Chart
BITDEER TECHNOLOGIES GROUP 5-Tage-Chart
RealtimeGeldBriefZeit
9,5679,72914:27
9,5659,72914:23
GlobeNewswire (Europe)
58 Leser
Artikel bewerten:
(0)

Bitdeer Technologies Group: Bitdeer Announces July 2026 Production and Operations Update

  • Colocation: $4.7B, 16-Year AI/HPC Data Center lease announced for Tydal, Norway Campus
  • AI Cloud: As of the reporting date, our 9.5MW A102 facility in Malaysia is fully committed under long-term offtake agreements, representing total expected contracted revenue exceeding $800 million. Additionally, contract discussions for the A201 facility (21.7MW IT Load) are currently underway. Demand is keen and strong. We expect to sign the contracts of A201 capacity and start collecting the advance payments within a month. We foresee the pricing of AI Cloud to increase further in the short-term future.
  • Bitcoin: Production increased 322% Y/Y to 1,190 Bitcoin.

Key Metrics Summary
AI Cloud Pipeline
(IT MW)
AI Cloud ARR1Colocation AI Data CenterSelf-Mining Hash Rate2Co-Mining Hash Rate3BTC Mined
141.4 MW~$76M$4.7B, 16-Year Lease with Volta at Tydal, Norway76.7 (EH/s)18.7 (EH/s)1,190

SINGAPORE, Aug. 26, 2026 (GLOBE NEWSWIRE) -- Bitdeer Technologies Group (NASDAQ: BTDR) ("Bitdeer" or the "Company"), a world-leading technology company for AI and Bitcoin mining infrastructure, today announced its unaudited operations updates for July 2026.

Management Commentary

"July reflected continued execution across our vertically integrated platform. Announcing our $4.7B, 16-year AI/HPC lease in early August marks a key milestone in converting our power portfolio into contracted, long-term revenue," said Michael G. Potter, Chief Financial Officer. "Our mining business continued to scale efficiently, reaching approximately 76.7 EH/s in self-mining hash rate. While our AI Cloud platform announced that as of today, our 9.5MW A102 facility in Malaysia is fully committed under long-term offtake agreements, representing total expected contracted revenue exceeding $800 million."

Bitdeer AI Update:

Colocation AI Data Center:

  • Bitdeer Announces $4.7 billion, 16-Year AI/HPC Data Center Lease for Tydal, Norway Campus
  • Approximately $4.7 billion in contracted revenue over the initial 16-year base-term, with the potential to reach a total contract value of $8.0 billion through a one-time 8-year lease extension.
  • Tenant is a subsidiary of Volta; the entire 121 IT MW will be configured to run NVIDIA GPUs for the end customer, a leading AI lab.
  • Credit backstop is anticipated to be arranged by affiliates of two leading top-tier global financial institutions via Letters of Credit, totaling approximately $1.3 billion and subject to customary conditions.
  • Tydal, Norway AI Data Center expected to be among Norway's largest and most efficient AI data centers upon completion. With a PUE of approximately 1.1 and running on 100% renewable energy, it sets a compelling standard for data center performance, at scale.

AI Cloud Key Metrics:

MetricJuly 2026June 2026
GPU Amount Deployed4,2484,248
GPU TypesH100, H200, B200, GB200, GB300H100, H200, B200, GB200, GB300
Utilization Rate895%95%
GPUs Under External Subscription3,5173,517
ARR1~$76M~$76M


AI Cloud Pipeline Update:

Data
Center
LocationIT Load
(MW)
GPU
Platform
DC RFSCloud
Contract
Status
Long Term
Contract
Coverage, %
DC Contract
A101Malaysia2.5GB200LiveLive100%Signed
A102Malaysia9.5GB300Nov 202650% signed, 50% contract in execution100%Signed
A201Malaysia21.7GB300 and small portion Vera RubinJan 2027 Signed
A401Norway42.7Vera Rubin2H 2027 Self-Owned
A501WA, USA10Vera RubinDec 2027 Self-Owned
A601TN, USA55Vera RubinOct 2027 Self-Owned
Total 141.4
  • As of the reporting date, A102's capacity in Malaysia has been fully committed under long-term offtake agreements ahead of energization, representing total expected revenue of over $800 million. Working on the contracts for the A201 facility now.
  • Strong Customer Demand for GPUs: As demand for AI computing continues to grow, we have completed the procurement of 66 NVIDIA GB300 systems.
  • Model Service & Token Optimization: Achieved Day-0 onboarding for NVIDIA Nemotron-3 Embed (1B & 8B) and launched Kimi K3 at the first available opportunity. Strategic engineering resources are now focused on expanding open-source model offerings and ensuring high service availability and reliability.
  • European Market Footprint: Further established Bitdeer AI's European presence through high-visibility participation at the RAISE Summit.
  • Ecosystem Acceleration: Co-hosted a month-long hackathon with NVIDIA, provisioning and mentoring 10 Southeast Asian teams with Bitdeer AI's GPU compute and Model Studio to demonstrate cross-industry business use cases.

Crypto Mining Update:

CRYPTO Mining, R&D, Manufacturing:

  • Mined 1,190 Bitcoins4, an increase of 322% Y/Y; we continue to expect momentum in our mining results over the coming months.
  • Self-mining hash rate reached ~76.7 EH/s.
  • Co-mining hashrate of 18.7 EH/s driven by Co-Mining collaboration, using Bitdeer's mining rigs operated by 3rd party datacenters.

Key Crypto Metrics:

MetricJuly 2026June 2026July 2025
Hash Rate Metrics:
Self-Mining (Operated in self-owned datacenters)76.773.022.3
Other Proprietary Hash Rate55.04.90.2
Total Proprietary Hash Rate6 (EH/s)81.777.922.5
Co-Mining (Operated by 3rd party datacenters)18.715.9-
BTC Mined41,190990282
BTC Held72571501,667


Infrastructure Summary:

Bitdeer will transition its infrastructure updates from a monthly reporting cadence to quarterly disclosures issued concurrently with its financial earnings releases, providing a more meaningful and integrated perspective on the Company's development progress. The Company's most recent infrastructure update was disclosed alongside its Q2 2026 financial results on August 10, 2026.

Upcoming Conferences & Events:

  • H.C. Wainwright & Co. 28th Annual Global Investment Conference - New York, September 14

Footnotes

1 ARR as of the last day of the respective month is calculated by multiplying the daily revenue generated from all contractually obligated GPU orders on that specific day by 365. This metric provides an annualized view of the revenue run-rate based on active contracts at the end of the reporting period.

2 Self-Mining (Operated in self-owned datacenters) refers to cryptocurrency mining for Bitdeer's own account, whereby its mining rigs are operated in self-owned datacenters

3 Co-mining (Operated by 3rd party datacenters) refers to cryptocurrency mining for Bitdeer's own account, whereby its mining rigs are operated by third-party datacenters

4 Includes BTC from self-mining operations and BTC from co-mining operations.

5 Other Proprietary Hash Rate includes the hashrate from Bitdeer's cloud hashrate business, mining rigs delivered in the crypto mining datacenters but not deployed and the mining rigs temporarily offline due to limited economic benefit.

6 Total Proprietary Hash Rate as of July 31, 2026 includes Self-Mining Hash Rate and Other Proprietary Hash Rate.

7 Bitcoins held does not include Bitcoins from customer deposits but does include Bitcoins that are pledged as collateral by us.

8 Utilization Rate as of the last day of the respective month is calculated as the total number of GPUs under internal and external orders divided by the total number of deployed GPUs.

About Bitdeer Technologies Group

Bitdeer is a world-leading technology company for AI and Bitcoin mining infrastructure. Bitdeer is committed to providing comprehensive Bitcoin mining solutions for its customers and building AI computational infrastructure to support the AI revolution. Bitdeer handles complex processes involved in computing such as equipment procurement, transport logistics, data center design and construction, equipment management, and daily operations. Bitdeer also offers advanced cloud capabilities to customers with high demand for artificial intelligence. Headquartered in Singapore, Bitdeer has deployed data centers across multiple countries, including the United States, Norway, Bhutan, and Ethiopia. To learn more, visit https://ir.bitdeer.com/ or follow Bitdeer on X- Bitdeer and LinkedIn @Bitdeer.

Investors and others should note that Bitdeer may announce material information using its website and/or on its accounts on social media platforms, including X, formerly known as Twitter, Facebook, and LinkedIn. Therefore, Bitdeer encourages investors and others to review the information it posts on social media and other communication channels listed on its website.

Forward-Looking Statements

Statements in this press release about future expectations, plans, and prospects, as well as any other statements regarding matters that are not historical facts, may constitute "forward-looking statements" within the meaning of The Private Securities Litigation Reform Act of 1995. The words "anticipate," "look forward to," "believe," "continue," "could," "estimate," "expect," "intend," "may," "plan," "potential," "predict," "project," "should," "target," "will," "would" and similar expressions are intended to identify forward-looking statements, although not all forward-looking statements contain these identifying words. Actual results may differ materially from those indicated by such forward-looking statements as a result of various important factors, including factors discussed in the section entitled "Risk Factors" in Bitdeer's annual report on Form 20-F, as well as discussions of potential risks, uncertainties, and other important factors in Bitdeer's subsequent filings with the U.S. Securities and Exchange Commission. Any forward-looking statements contained in this press release speak only as of the date hereof. Bitdeer specifically disclaims any obligation to update any forward-looking statement, whether due to new information, future events, or otherwise. Readers should not rely upon the information on this page as current or accurate after its publication date.

For investor and media inquiries, please contact:

Investor Relations
Tesh Dahya, Head of Investor Relations
tesh.dahya@bitdeer.com

Media
Elev8 New Media
Jessica Starman, MBA
bitdeer@elev8newmedia.com


© 2026 GlobeNewswire (Europe)
KI braucht Strom
Halbleiter, Speicherchips und Rechenzentren haben Anlegern im KI-Boom bereits enorme Gewinne beschert. Doch jetzt zeichnet sich mit der benötigten Energie der nächste große Flaschenhals ab. Neue KI-Rechenzentren benötigen nicht mehr einige Megawatt, sondern zum Teil mehrere Gigawatt Leistung – so viel wie mehrere moderne Kernkraftwerksblöcke.

Damit beginnt ein weltweites Wettrennen um verfügbare Stromkapazitäten. Hyperscaler sichern sich bereits über langfristige Verträge gewaltige Energiemengen, während Stromnetze und Erzeugungskapazitäten mit dem Ausbau kaum Schritt halten können. Zusätzlich verschärfen geopolitische Risiken rund um den Iran-Krieg und die Straße von Hormus die Situation.

Für Energieversorger und ihre Zulieferer könnte damit ein goldenes Zeitalter beginnen. Steigende Nachfrage, langfristige Abnahmeverträge und wachsende Strompreise schaffen ein Umfeld, in dem ausgewählte Unternehmen zum nächsten großen KI-Trade werden könnten.

In unserem aktuellen Spezialreport stellen wir fünf Aktien vor, die besonders stark vom explodierenden Energiehunger der KI profitieren könnten – und bei Anlegern bislang teilweise noch unter dem Radar laufen.

Jetzt den kostenlosen Report sichern – und die nächsten Gewinner des KI-Booms entdecken!
Werbehinweise: Die Billigung des Basisprospekts durch die BaFin ist nicht als ihre Befürwortung der angebotenen Wertpapiere zu verstehen. Wir empfehlen Interessenten und potenziellen Anlegern den Basisprospekt und die Endgültigen Bedingungen zu lesen, bevor sie eine Anlageentscheidung treffen, um sich möglichst umfassend zu informieren, insbesondere über die potenziellen Risiken und Chancen des Wertpapiers. Sie sind im Begriff, ein Produkt zu erwerben, das nicht einfach ist und schwer zu verstehen sein kann.