Orvana Announces Update on Resource and Reserve Estimates, Operations, and Drill Results at El Valle-Boinas/Carles Gold/Copper Mine, Northern Spain

TORONTO, ONTARIO -- (Marketwire) -- 02/21/12 -- Orvana Minerals Corp. (TSX: ORV) ("Orvana" or the "Company") is pleased to announce an update on reserve estimates, operations, and drill results for its El Valle-Boinas/Carles ("EVBC") gold-copper mine in northern Spain by Kinbauri Espana S.L.U. ("Kinbauri"), a wholly-owned subsidiary of Orvana.

Resource Estimate

The updated resource estimate included an additional 72 drill holes for 8,770 metres drilled from September, 2010 through August, 2011. Based on a 2 gram per tonne gold cutoff, measured and indicated gold ounces are about 1,300,000, an increase of 95,000 ounces as compared to the previous resource estimate (see press release of March 5, 2010). The inferred gold resources are over 1,300,000 ounces. The table below summarizes the updated resource estimate.

---------------------------------------------------------
                   EVBC Resource Estimates - August 2011 (2 g/t gold cutoff)
----------------------------------------------------------------------------
----------------------------------------------------------------------------
                            Measured                     Indicated
----------------------------------------------------------------------------
                 tonnes, Gold, Copper, Silver, tonnes, Gold, Copper, Silver,
ZONE               '000s   g/t       %     g/t   '000s   g/t       %     g/t
----------------------------------------------------------------------------
TOTAL BOINAS
OXIDES                 -     -       -       -   2,290  7.07    0.52       -
----------------------------------------------------------------------------
TOTAL BOINAS
SKARNS             1,976  3.85    0.81       -   2,246  4.08    0.76       -
----------------------------------------------------------------------------
TOTAL CARLES         731  4.35    0.59       -   1,079  3.87    0.42       -
----------------------------------------------------------------------------
TOTAL EVBC         2,707  3.99    0.75       -   5,615  5.26    0.60       -
----------------------------------------------------------------------------
----------------------------------------------------------------------------
Measured &
Indicated          8,323  4.84    0.65       -
                   ---------------------------



                   -------------------------------------
                   EVBC Resource Estimates - August 2011
                            (2 g/t gold cutoff)
--------------------------------------------------------
--------------------------------------------------------
                                  Inferred
                   -------------------------------------
                     tonnes,    Gold,   Copper,  Silver,
ZONE                   '000s      g/t         %      g/t
--------------------------------------------------------
TOTAL BOINAS
OXIDES                 3,939     5.51      0.35        -
--------------------------------------------------------
TOTAL BOINAS
SKARNS                 2,894     4.40      0.48        -
--------------------------------------------------------
TOTAL CARLES           1,562     4.20      0.35        -
--------------------------------------------------------
TOTAL EVBC             8,395     4.88      0.39        -
--------------------------------------------------------
--------------------------------------------------------
Note: Silver grades are not reported because silver
resources were not estimated for all ore bodies within
the three zones.

Reserve Estimate

An updated reserve estimate and mine plan was developed based on the aforementioned resource estimate. This estimate shows an increase of 28,000 ounces of gold as compared to the previous estimate (see press release of July 14, 2010).

----------------------------------------------------------------------------
                            Proven                       Probable
                 -----------------------------------------------------------
                 tonnes, Gold, Copper, Silver, tonnes, Gold, Copper, Silver,
ZONE               '000s   g/t       %     g/t   '000s   g/t       %     g/t
----------------------------------------------------------------------------
TOTAL BOINAS
OXIDES                 -     -       -       -   2,586  4.37    0.35       -
----------------------------------------------------------------------------
TOTAL BOINAS
SKARNS             1,557  2.88    0.66   15.25   1,982  2.78    0.73   14.94
----------------------------------------------------------------------------
TOTAL CARLES         361  3.36    0.61       -   1,180  2.34    0.30       -
----------------------------------------------------------------------------
TOTAL EVBC         1,918  2.97    0.65       -   5,748  3.40    0.47       -
----------------------------------------------------------------------------


----------------------------------------------
                         Proven & Probable
                 -----------------------------
                 tonnes, Gold, Copper, Silver,
ZONE               '000s   g/t       %     g/t
----------------------------------------------
TOTAL BOINAS
OXIDES             2,586  4.37    0.35       -
----------------------------------------------
TOTAL BOINAS
SKARNS             3,539  2.83    0.70   15.07
----------------------------------------------
TOTAL CARLES       1,541  2.58    0.37       -
----------------------------------------------
TOTAL EVBC         7,667  3.30    0.52       -
----------------------------------------------
Note: Silver grades are reported for the
Boinas skarns because measured and indicated
silver resources were estimated for those ore
bodies that are converted to proven and
probable reserves

The decrease in gold grade as compared to the previous estimate is a result of a mine-strategy review, more detailed engineering design, and the application of other mining factors, all of which were based on experience gained during 2011 operations. Given that the shaft is scheduled for commissioning in April, 2012, it was decided to bulk mine the El Valle/Boinas skarns by longhole stoping methods, followed by backfill, as opposed to the more selective cut-and-fill methods in certain areas. The bulk mining of the skarns requires less development for stope preparation and results in greater productivity. In addition, drill-and-blast methods will be replaced by mechanized mining methods for exploitation of the subvertical, higher-grade gold, oxide mineralization; although dilution is expected to be less than that planned for conventional mining, dilution factors remain conservative. Finally, unplanned dilution and ore loss were factored into this reserve estimate.

The projected production over the next ten years is summarized in the table below. Cash operating costs, including royalties, are estimated at $700-800 per ounce of gold net of by-product revenues using a price deck of $1,100 per ounce of gold, $2.75 per pound of copper, and $20 per ounce of silver. Input recoveries are 90% for gold, 67% for copper, and 60% for silver, all of which are lower than the current actual recoveries (see below).

EVBC 2011 Mine Plan - Production Projections
--------------------------------------------------------
Fiscal        Gold,       Copper,                Silver,
Year         ounces        tonnes                 ounces
--------------------------------------------------------
--------------------------------------------------------
2012         60,000         2,000                150,000
2013         65,000         2,300                139,000
2014         86,000         3,000                183,000
2015         76,000         2,600                161,000
2016         59,000         1,600                 99,000
2017         78,000         2,200                137,000
2018         95,000         3,000                172,000
2019         86,000         3,500                203,000
2020         69,000         2,700                134,000
2021         58,000         2,800                121,000
      Note: Fiscal year is October 1-September 30

Operations

Production for January was 38,730 tonnes with a head grade of 2.57 grams per tonne gold, 0.40% copper, and 10.3 grams per tonne silver; recoveries were 93.3%, 85.7%, and 79.4%, respectively, resulting in 2,980 ounces of gold, 295,890 pounds of copper, and 10,141 ounces of silver. 46% of the gold and 11% of the silver were produced as dore, which dore consisted of 55% gold and 45% silver. Cash operating costs, including royalties, were $710 per ounce of gold net of by-product revenues.

Earlier in the month, the shaft reaming and disassembly of the reamer were completed. Installation of both underground and surface infrastructure progresses as planned. Shaft commissioning is scheduled for April.

Currently, roadheaders are mining the Charnela and A107 (330 level) subvertical, high-grade gold structures. At level 80, mining of the San Martin skarn continues in one stope and an adjacent stope is being developed; development to access levels 100 and 120 is in progress. Boinas East ore is constantly being fed to the plant. At Carles, mining currently proceeds at the -10, -40 and -80 levels.

Drilling

Underground drilling continues both at El Valle/Boinas and Carles. Whereas the focus of the drilling was for mine development, many of the holes were step-outs beyond known NI 43-101-compliant resources and reserves. The table below is a summary of select results.

----------------------------------------------------
                                         True
                      From,    To, Thickness,   Au,  Ag,  Cu,
         HOLE        metres metres     metres   g/t  g/t    %
-------------------------------------------------------------
-------------------------------------------------------------
         11CNW1005   203.35 238.65       7.06  3.43  1.8 0.09
CARLES   11CNW1006   173.50 176.75       2.54  4.53  1.9 0.04
         11CNW1007    191.5  198.4       2.42  2.57  1.4 0.04
-------------------------------------------------------------
         Boinas East (BE)
         11BE1030    143.85 146.40       2.55  3.21 12.3 0.29
         11BE1031    241.20 242.65       1.12  4.72 18.8 0.25
         11BE1032      0.00   5.00       4.85  2.16 23.8 0.63
         11BE1032     47.60  50.00       2.33  3.00 29.4 0.70
         ----------------------------------------------------
         San Martin (SM)
         11V1206     150.20 191.85      10.41  4.92 21.0 0.85
          including  158.55 178.55       5.00  6.85 30.8 1.23
         ----------------------------------------------------
EL       11V1207      51.65  66.95       5.36  5.19 68.6 3.13
VALLE-   11V1207     110.15 132.85       7.95 34.28  4.3 4.72
BOINAS   ----------------------------------------------------
         11V1208     148.55 153.65       2.04  5.57 31.3 0.61
         11V1208     159.70 170.20       4.20  3.36  4.1 0.08
         ----------------------------------------------------
         11V1209     132.40 141.90       3.33  2.64 15.7 0.65
         11V1209     182.50 186.50       1.40  4.37 37.2 0.77
         ----------------------------------------------------
         11V1210      18.80  29.85       2.21  8.91 21.4 0.41
         11V1210     106.90 151.65       8.95  5.04 35.8 1.24
         ----------------------------------------------------
         11V1211       4.50   6.00       0.75  9.63  1.0 0.00
         ----------------------------------------------------
         11V1212      15.20  22.15       5.35  5.84 26.3 1.77
         11V1212      72.40  76.30       3.00  4.41 20.4 1.59
         11V1212      86.60 103.40      12.94  3.38 26.5 0.83
         ----------------------------------------------------
         11V1213      25.80  28.80       2.25  7.00 67.0 3.07
-------------------------------------------------------------


         --------------------------------

          Recovery
                 %       ZONE     Purpose
-----------------------------------------
-----------------------------------------
             98.44  NorthWest Exploration
CARLES      100.00  NorthWest Exploration
            100.00  NorthWest Exploration
-----------------------------------------
         Boinas East (BE)
            100.00  Boinas E.    Step Out
            100.00  Boinas E.    Step Out
             96.00  Boinas E.    Step Out
            100.00  Boinas E.    Step Out
         --------------------------------
         San Martin (SM)
             93.88 San Martin      Infill
             95.00 San Martin      Infill
         --------------------------------
EL          100.00 San Martin      Infill
VALLE-       97.50 San Martin      Infill
BOINAS   --------------------------------
             97.06 San Martin      Infill
             99.05 San Martin      Infill
         --------------------------------
            100.00 San Martin      Infill
            100.00 San Martin      Infill
         --------------------------------
             96.83 San Martin      Infill
             86.37 San Martin      Infill
         --------------------------------
             93.33 San Martin      Infill
         --------------------------------
             98.56 San Martin      Infill
             98.72 San Martin      Infill
             99.11 San Martin      Infill
         --------------------------------
             98.33 San Martin      Infill
-----------------------------------------
Note: True thicknesses were determined
graphically by measuring the distance
approximately perpendicular to the
contacts. No values were capped.

None of these drill holes were included in the resource and reserve estimates reported herein. Current drilling is focused on the higher-grade San Martin skarn, specifically proximal to the stopes currently being mined and developed.

More information related to the EVBC geology and mineralization can be found on the Company's website www.orvana.com. The NI 43-101 technical report detailing the information herein will be available on www.sedar.com and the Company's website within 45 days.

QA/QC

Security measures were taken to ensure the integrity and validity of the mineralization and proximal rocks in the new drill core under the supervision of Santiago Gonzalez-Nistal, Chief Geologist, Kinbauri Espana S.L.U., a qualified person for the purposes of NI 43-101. The core was sampled based on lithologic and alteration considerations. Assays for the samples were analyzed at Kinbauri Espana SLU laboratory on site; pulps were sent to ALS Chemex for check analyses. The QA/QC protocol included internal and laboratory certified reference materials, blanks, duplicates and check assays. At the EVBC laboratory, a 30-gram sample was analyzed by fire assay methods for gold, and copper, silver, arsenic and antimony were analyzed by ICP-optical emission spectroscopy after an agua regia digestion. Also, a 30-gram sample was analyzed by fire assay methods for gold and a conventional ICP-AES analysis was used for the analysis of 35 elements at ALS Chemex.

Qualified Persons

The resource estimate was prepared by Ore Reserves Engineering under the supervision of A. Noble, P.E., an independent qualified person for the purposes of NI 43-101. The reserve estimate and mine plan were prepared by Adam Wheeler, C.Eng. and Bob Dowdell, C.Eng., both of whom are independent qualified persons for the purposes of NI 43-101. The other technical information contained in this document was prepared under the supervision of Santiago Gonzalez-Nistal, Chief Geologist, Kinbauri Espana S.L.U. and Bill Williams, Ph.D., CPG, President and CEO of Orvana, both of whom are qualified persons for the purposes of NI 43-101.

About Orvana

Orvana is a multi-mine gold and copper producer. Orvana's primary asset is the El Valle/Boinas-Carles gold-copper project in northern Spain. Orvana also owns the Don Mario Mine in Bolivia, where the mining and processing of the copper-gold-silver Upper Mineralized Zone deposit remains in the commissioning stage. Orvana recently announced a feasibility study on its Copperwood copper project in Michigan, USA. Additional information is available at Orvana's website (www.orvana.com).

Forward Looking Disclaimer

Certain statements in this press release constitute forward-looking statements or forward-looking information within the meaning of applicable securities laws ("forward-looking statements"). Any statements that express or involve discussions with respect to predictions, expectations, beliefs, plans, projections, objectives, assumptions, potentials, future events or performance (often, but not always, using words or phrases such as "believes", "expects " "plans", "estimates" or "intends" or stating that certain actions, events or results "may", "could", "would", "might", "will" or "are projected to" be taken or achieved) are not statements of historical fact, but are forward-looking statements.

Forward-looking statements relate to, among other things, all aspects of the development of the Upper Mineralized Zone ("UMZ") deposit at the Don Mario Mine in Bolivia, the El Valle-Boinas/Carles project in Spain and the Copperwood project in Michigan and their potential operations and production; the outcome and timing of decisions with respect to whether and how to proceed with such development and production; the timing and outcome of any such development and production; estimates of future capital expenditures; mineral resource estimates; estimates of permitting time lines; statements and information regarding future feasibility studies and their results; production forecasts; future transactions; future metal prices; the ability to achieve additional growth and geographic diversification; future production costs; future financial performance, including the ability to increase cash flow and profits; future financing requirements; and mine development plans.

Forward-looking statements are necessarily based upon a number of estimates and assumptions that, while considered reasonable by Orvana as of the date of such statements, are inherently subject to significant business, economic and competitive uncertainties and contingencies. The estimates and assumptions of Orvana contained or incorporated by reference in this news release, which may prove to be incorrect, include, but are not limited to, the various assumptions set forth herein and in the Company's most recently filed Annual Information Form, or as otherwise expressly incorporated herein by reference as well as: there being no significant disruptions affecting operations, whether due to labour disruptions, supply disruptions, power disruptions, damage to equipment or otherwise; permitting, development, operations, expansion and acquisitions at the UMZ deposit, El Valle-Boinas/Carles and the Copperwood projects being consistent with the Company's current expectations; political developments in any jurisdiction in which the Company operates being consistent with its current expectations; certain price assumptions for gold, copper and silver; prices for key supplies being approximately consistent with current levels; production and cost of sales forecasts meeting expectations; the accuracy of the Company's current mineral reserve and mineral resource estimates; and labour and materials costs increasing on a basis consistent with Orvana's current expectations.

A variety of inherent risks, uncertainties and factors, many of which are beyond the Company's control, affect the operations, performance and results of the Company and its business, and could cause actual events or results to differ materially from estimated or anticipated events or results expressed or implied by forward looking statements. Some of these risks, uncertainties and factors include fluctuations in the price of gold, silver and copper; the need to recalculate estimates of resources based on actual production experience; the failure to achieve production estimates; variations in the grade of ore mined; variations in the cost of operations; the availability of qualified personnel; the Company's ability to obtain and maintain all necessary regulatory approvals and licenses; the Company's ability to use cyanide in its mining operations; risks generally associated with mineral exploration and development, including the Company's ability to develop the UMZ deposit, the Copperwood project or the El Valle-Boinas/Carles project; the Company's ability to acquire and develop mineral properties and to successfully integrate such acquisitions; the Company's ability to obtain financing when required on terms that are acceptable to the Company; challenges to the Company's interests in its property and mineral rights; current, pending and proposed legislative or regulatory developments or changes in political, social or economic conditions in the countries in which the Company operates; general economic conditions worldwide; and the risks identified in Orvana's Management's Discussion and Analysis for the period ended September 30, 2009 under the heading "Risks and Uncertainties". This list is not exhaustive of the factors that may affect any of the Company's forward-looking statements and reference should also be made to the Company's Annual Information Form for a description of additional risk factors.

Forward-looking statements are based on management's current plans, estimates, projections, beliefs and opinions and, except as required by law, the Company does not undertake any obligation to update forward-looking statements should assumptions related to these plans, estimates, projections, beliefs and opinions change. Readers are cautioned not to put undue reliance on forward-looking statements.

Contacts:
Orvana Minerals Corp.
Natalie Frame
Investor Relations
(289) 200-7640

Orvana Minerals Corp.
Bill Williams
President and Chief Executive Officer
ask_us@orvana.com
www.orvana.com

Kinbauri Espana S.L.U.
Agne Ahlenius
Director General

© 2012 Marketwired
Software vor dem Comeback – diese 5 Aktien könnten durchstarten!
Während Halbleiter- und KI-Infrastrukturwerte von einem Hoch zum nächsten jagen, wurden viele Software-Aktien in den vergangenen Monaten regelrecht aus den Depots gedrängt. Die Angst vor Disruption hat Investoren zu einem radikalen Strategiewechsel veranlasst – mit der Folge, dass zahlreiche Qualitätsunternehmen heute auf Mehrjahrestiefs notieren.

Doch genau hier entsteht eine seltene Chance. Denn während die Bewertungen im Halbleitersektor inzwischen auf ambitionierten Niveaus liegen, ist der Bewertungsabschlag bei Software-Titeln so hoch wie seit Jahren nicht mehr. Gleichzeitig liefern viele Unternehmen weiterhin starke Wachstumszahlen und integrieren KI erfolgreich in ihre Geschäftsmodelle. Die Diskrepanz zwischen Kursentwicklung und operativer Stärke könnte sich schon bald auflösen.

Für Anleger bedeutet das: antizyklisch denken und gezielt zugreifen, bevor der Markt dreht. Denn erste technische Signale deuten darauf hin, dass sich die Trendwende bereits anbahnt.

In unserem aktuellen Spezialreport stellen wir fünf Software-Aktien vor, die besonders aussichtsreich positioniert sind – mit starker Marktstellung, attraktiver Bewertung und hohem Aufholpotenzial.

Jetzt den kostenlosen Report sichern – bevor der Software-Rebound Fahrt aufnimmt!
Werbehinweise: Die Billigung des Basisprospekts durch die BaFin ist nicht als ihre Befürwortung der angebotenen Wertpapiere zu verstehen. Wir empfehlen Interessenten und potenziellen Anlegern den Basisprospekt und die Endgültigen Bedingungen zu lesen, bevor sie eine Anlageentscheidung treffen, um sich möglichst umfassend zu informieren, insbesondere über die potenziellen Risiken und Chancen des Wertpapiers. Sie sind im Begriff, ein Produkt zu erwerben, das nicht einfach ist und schwer zu verstehen sein kann.