Donner Metals Ltd.: Bracemac-Mcleod Continues on Target

VANCOUVER, BRITISH COLUMBIA -- (Marketwire) -- 09/05/12 -- Mr. Harvey Keats, Chief Executive Officer of Donner Metals Ltd. ("Donner Metals" or the "Company") (TSX VENTURE: DON)(FRANKFURT: D4M), is pleased to provide an update on the development for the Bracemac-McLeod Mine as reported to the Company by partner and project operator Xstrata Canada Corporation-Xstrata Zinc Canada Division ("Xstrata Zinc").

Multi-face development continues on 9 fronts and total lateral development now stands at 5,550 metres. Mine pre-production activities should be completed by year-end and the initial production is on schedule to begin in the first quarter of 2013. The project is tracking on budget, with the contingency allocated to the additional ball mill. The status of project development at Bracemac-McLeod is summarized as follows:

Surface:

----------------------------------------------------------------------------
Site administration facilities and infrastructure                 Existing
----------------------------------------------------------------------------
Matagami mill infrastructure (upgraded in 2007-2008)              Existing
----------------------------------------------------------------------------
Tailings facility                                                 Existing
----------------------------------------------------------------------------
Railroad and highway (zinc and copper concentrate                 Existing
shipping)
----------------------------------------------------------------------------
Haulage road to Matagami mill                                     Complete
----------------------------------------------------------------------------
Ramp portal                                                       Complete
----------------------------------------------------------------------------
Stockpile and waste rock pads                                     Complete
----------------------------------------------------------------------------
Service access road to portal                                     Complete
----------------------------------------------------------------------------
Power, water service and mine water line to                       Complete
treatment facilities
----------------------------------------------------------------------------
Power and access to vent/fill raise sites                         Complete
----------------------------------------------------------------------------
Electrical substation at Bracemac                                 Complete
----------------------------------------------------------------------------
Communication tower at Bracemac                                   Complete
----------------------------------------------------------------------------
Permanent surface mine dewatering pumping station                 Complete
----------------------------------------------------------------------------
Remaining Perseverance personnel relocation to                    Complete
Matagami Lake complex
----------------------------------------------------------------------------
Surface garage and support buildings (to be                       Complete
augmented by Perseverance buildings)
----------------------------------------------------------------------------
Perseverance office building transfer                In progress
----------------------------------------------------------------------------
Perseverance garage transfer                         In progress
----------------------------------------------------------------------------
Permanent parking lot                                In progress
----------------------------------------------------------------------------
Mill and tailing capacity increase                   In progress
----------------------------------------------------------------------------
Additional ball mill to increase grinding capacity   In progress
----------------------------------------------------------------------------

Underground:

----------------------------------------------------------------------------
Ramp to Bracemac area and underground power supply                Complete
at Bracemac
----------------------------------------------------------------------------
Fill raise construction                                           Complete
----------------------------------------------------------------------------
Temporary ventilation in fill raise                               Complete
----------------------------------------------------------------------------
Temporary heating units relocated from Perseverance               Complete
to Bracemac
----------------------------------------------------------------------------
Underground powder magazine and cap magazine                      Complete
----------------------------------------------------------------------------
Underground electrical substation                                 Complete
----------------------------------------------------------------------------
Equipment purchase and transfer from the            Ongoing
Perseverance Mine
----------------------------------------------------------------------------
Underground garage at Bracemac                      In progress
----------------------------------------------------------------------------
Vent raise construction                             In progress
----------------------------------------------------------------------------
Underground dewatering system                       In progress
----------------------------------------------------------------------------
Underground storage #1                                            Complete
----------------------------------------------------------------------------
Underground storage #2 and #3                       In progress
----------------------------------------------------------------------------
Refuge station #1 and #2                                          Complete
----------------------------------------------------------------------------
Refuge station #3                                   In progress
----------------------------------------------------------------------------
Ramps to McLeod zone                                In progress
----------------------------------------------------------------------------
Multi-face development to Bracemac ore lenses       In progress
----------------------------------------------------------------------------
Definition diamond drilling at Bracemac             In progress
----------------------------------------------------------------------------

Donner Metals' CEO Harvey Keats commented on the progress made and ongoing construction saying, "As can be seen from the details of the project development, both on the surface and underground, Bracemac-McLeod is poised to replace the Perseverance Mine in feeding the Matagami mill."

SUPPLEMENTARY INFORMATION

The Bracemac-McLeod deposit contains Proven and Probable Mineral Reserves of 3.7 million tonnes grading 9.60% zinc, 1.26% copper, 28.25g/t silver and 0.43g/t gold. Inferred Mineral Resources of 2.6 million tonnes grading 8.79% zinc, 1.31% copper, 38.84g/t silver and 1.06g/t gold are located in proximity to the Mineral Reserves.

The Company is a fully vested partner with Xstrata Canada Corporation in the extensive Matagami base metal camp located in the Abitibi region of Quebec. This joint venture partnership covers six joint venture areas ("the Matagami Project") governing 4,737 square kilometres of prime stratigraphy, which has yielded high-grade base metal production since 1963. Xstrata Zinc is the project operator for the Matagami Project, including the Bracemac-McLeod Mine. Additional information is available at www.donnermetals.com.

Robin Adair (VP of Exploration) is a Qualified Person for Donner Metals Ltd. and is responsible for the technical information reported in this news release.

ON BEHALF OF THE BOARD OF DONNER METALS LTD.

Harvey Keats, Chief Executive Officer

Cautionary Statement:

Certain phrases in this news release are "forward-looking statements". Forward-looking statements are identified by wording such as "should be," and "is on schedule." Such statements are applicable specifically to the Bracemac-McLeod Deposit in relation to: 1) the possible future completion of development as scheduled under the current development plan, 2) mining/production in relation to the current mining plan and 3) future planned exploration activities. Such statements also pertain to the completion of the project within context of the budget as defined in the feasibility study completed by Xstrata Canada Corporation - Xstrata Zinc Canada Division and Genivar Limited Partnership in 2010. With respect to future production, and the commencement thereof, from the Bracemac-McLeod deposit, the forward looking statements are in the context of the feasibility study completed by Xstrata Canada Corporation - Xstrata Zinc Canada Division and Genivar Limited Partnership in 2010 as posted under the Company's profile at www.sedar.com. "Forward-looking statements" involve known and unknown risks, uncertainties and other factors which may cause actual results, performance or achievements of the Company to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements. Further discussion of "forward looking statements" and "future oriented financial information" and the risks inherent to mineral exploration and development, in relation to Donner's activities, can be found on the Company's website at www.donnermetals.com. The reader is cautioned not to place any undue reliance on any forward-looking statement.

NEITHER THE TSX VENTURE EXCHANGE NOR ITS REGULATION SERVICES PROVIDER (AS THAT TERM IS DEFINED IN THE POLICIES OF THE TSX VENTURE EXCHANGE) ACCEPTS RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THIS NEWS RELEASE.

Contacts:
Donner Metals Ltd.
Andrea Magee
(604) 683-0564 or Toll Free: 1-800-909-8311
(604) 602-9311 (FAX)
donner@bed-rock.com
www.donnermetals.com

© 2012 Marketwired
Software vor dem Comeback – diese 5 Aktien könnten durchstarten!
Während Halbleiter- und KI-Infrastrukturwerte von einem Hoch zum nächsten jagen, wurden viele Software-Aktien in den vergangenen Monaten regelrecht aus den Depots gedrängt. Die Angst vor Disruption hat Investoren zu einem radikalen Strategiewechsel veranlasst – mit der Folge, dass zahlreiche Qualitätsunternehmen heute auf Mehrjahrestiefs notieren.

Doch genau hier entsteht eine seltene Chance. Denn während die Bewertungen im Halbleitersektor inzwischen auf ambitionierten Niveaus liegen, ist der Bewertungsabschlag bei Software-Titeln so hoch wie seit Jahren nicht mehr. Gleichzeitig liefern viele Unternehmen weiterhin starke Wachstumszahlen und integrieren KI erfolgreich in ihre Geschäftsmodelle. Die Diskrepanz zwischen Kursentwicklung und operativer Stärke könnte sich schon bald auflösen.

Für Anleger bedeutet das: antizyklisch denken und gezielt zugreifen, bevor der Markt dreht. Denn erste technische Signale deuten darauf hin, dass sich die Trendwende bereits anbahnt.

In unserem aktuellen Spezialreport stellen wir fünf Software-Aktien vor, die besonders aussichtsreich positioniert sind – mit starker Marktstellung, attraktiver Bewertung und hohem Aufholpotenzial.

Jetzt den kostenlosen Report sichern – bevor der Software-Rebound Fahrt aufnimmt!
Werbehinweise: Die Billigung des Basisprospekts durch die BaFin ist nicht als ihre Befürwortung der angebotenen Wertpapiere zu verstehen. Wir empfehlen Interessenten und potenziellen Anlegern den Basisprospekt und die Endgültigen Bedingungen zu lesen, bevor sie eine Anlageentscheidung treffen, um sich möglichst umfassend zu informieren, insbesondere über die potenziellen Risiken und Chancen des Wertpapiers. Sie sind im Begriff, ein Produkt zu erwerben, das nicht einfach ist und schwer zu verstehen sein kann.