Fortuna Silver Mines Inc.: Fortuna reports 2017 production of 11.9 million silver equivalent ounces and issues guidance for 2018

VANCOUVER, British Columbia, 2018-01-17 11:00 CET (GLOBE NEWSWIRE) --
Fortuna Silver Mines, Inc. (NYSE:FSM) (TSX:FVI) is pleased to announce 2017
production figures from its two underground operating silver mines, the San
Jose Mine in Mexico and the Caylloma Mine in Peru.  The company produced 8.5
million ounces of silver and 56.4 thousand ounces of gold or 11.9 million AgEq1
ounces. 

2017 Consolidated Production Highlights

  -- Silver and gold production were 4 % and 8 % respectively above 2017
     guidance
  -- Silver production of 8,469,593 ounces; 15 % increase over 2016 
  -- Gold production of 56,441 ounces; 21 % increase over 2016
  -- Zinc production of 44,347,035 pounds; 3 % increase over 2016 
  -- Lead production of 29,877,890 pounds; 9 % decrease over 2016

Note: 1. Silver equivalent is calculated using silver to gold ratio of 60 to 1

2017 Consolidated Operating Results

                              Q4 2017                           2017            
                 Caylloma,  San Jose,  Consolidat  Caylloma,  San     Consolidat
                 Peru       Mexico         ed      Peru        Jose,      ed    
                                                              Mexico            
Processed Ore                                                         
Tonnes milled      134,635    271,370                529,704  1,070,            
                                                                 791            
Average tpd          1,496      3,015                  1,484   3,035            
 milled                                                                         
Silver                                                                
Grade (g/t)             65        259                     66     238            
Recovery (%)         84.69      91.86                  84.31   91.82            
Production (oz)    238,414  2,071,762   2,310,176    943,038  7,526,   8,469,593
                                                                 555            

                            Q4 2017                           2017              
                Caylloma,   San     Consolidate  Caylloma,   San     Consolidate
                Peru         Jose,  d            Peru         Jose,       d     
                            Mexico                           Mexico             
Gold                                                                 
Grade (g/t)           0.18    1.89                     0.18    1.77             
Recovery (%)         13.85   92.17                    15.87   91.62             
Production             106  15,177       15,283         491  55,950       56,441
 (oz)                                                                           
Lead                                                                 
Grade (%)             2.91                             2.81                     
Recovery (%)         90.75                            91.06                     
Production       7,846,302            7,846,302  29,877,890           29,877,890
 (lbs)                                                                          
Zinc                                                                 
Grade (%)             4.36                             4.21                     
Recovery (%)         90.14                            90.23                     
Production      11,676,397           11,676,397  44,347,035           44,347,035
 (lbs)                                                                          

Note: Metallurgical recovery for silver at the Caylloma Mine is calculated
based on silver content in lead concentrate 

San Jose Mine, Mexico

The San Jose Mine produced 2,071,762 ounces of silver and 15,177 ounces of gold
in the fourth quarter, 15 % and 16 % above budget respectively.  Average head
grades for silver and gold were 259 g/t and 1.89 g/t, 12 % and 13 % above
budget respectively. 

Silver and gold production for 2017 totaled 7.5 million ounces and 55,950
ounces respectively; being 5 % and 8 % above the mine's annual guidance. 
Average head grades for silver and gold were 238 g/t and 1.77 g/t, 3 % and 6 %
above the mine's annual guidance respectively. 

In 2017, mine production was sourced from Trinidad Central and Trinidad North
with each area contributing 57 % and 43 % of ore respectively.  The processing
plant treated an average of 3,035 tpd. 

Caylloma Mine, Peru

The Caylloma Mine produced 238,414 ounces of silver in the fourth quarter, 8 %
below budget.  Average silver head grade of 65 g/t, 13 % below budget, was
offset by higher metallurgical recovery of 84.69%, 6 % above budget. 

Silver production for 2017 totaled 943,038 ounces; 4 % below the mine's annual
guidance. Average head grade for silver was 66 g/t, 7 % below the mine's annual
guidance. 

Lead and zinc production for the fourth quarter was 7,846,302 pounds and
11,676,397 pounds respectively, 4 % below budget and 13 % above budget. 
Average head grades for lead and zinc were 2.91% and 4.36%, 1 % below budget
and 13 % above budget respectively. 

Base metals production for 2017 totaled 29,877,890 pounds of lead and
44,347,035 pounds of zinc; in line with annual guidance and 8 % above the
mine's annual guidance, respectively. Average head grades for lead and zinc
were 2.81% and 4.21%, 3 % and 9 % above annual guidance. 

In 2017, mine production was sourced primarily from the Animas NE and Animas
Central areas with each contributing 58 % and 32 % of ore respectively.  The
processing plant treated an average of 1,484 tpd. 

2018 Consolidated Production and Cash Cost Guidance

                       Silver   Gold    Lead     Zinc    Cash Cost    AISC1  
                        (Moz)  (koz)   (Mlbs)    (Mlbs)    ($/t)    ($/oz Ag)
                       
San Jose Mine, Mexico   7.5     48.3       NA    NA       61.2        6.6    
Caylloma Mine, Peru     0.8     --        25.8  44.8      81.3       (5.2  ) 
                Total   8.3     48.3      26.5  44.1                         

  -- 2018 silver equivalent2 production guidance of 11.4 million ounces
  -- 2018 consolidated AISC1 of $6.8/oz Ag

Notes:

  1. All-in sustaining cash cost (AISC) per ounce of silver is net of
     by-products gold, lead and zinc; see appendix for breakdown
  2. Silver equivalent production does not include lead or zinc and is
     calculated using a silver to gold ratio of 65 to 1
  3. Total figures may not add due to rounding

2018 Outlook

San Jose Mine, Mexico

San Jose plans to process 1,050,000 tonnes of ore averaging 240 g/t Ag and 1.56
g/t Au. Capital investments are estimated at $16.9 million; includes $8.5
million for sustaining CAPEX1 and $8.4 million for exploration programs. 

Major capital investment projects include:

  -- Mine development:                                  $3.5 million
  -- Equipment and infrastructure:                 $4.1 million

Note: 1. Capital Expenditure

Caylloma Mine, Peru

Caylloma plans to process 535,500 tonnes of ore averaging 57 g/t Ag, 2.41% Pb
and 4.21% Zn. Capital investments are estimated at $21.3 million; including
$16.4 million for sustaining CAPEX, $2.8 million for non-sustaining CAPEX, and
$2.2 million for Brownfields exploration programs. 

Major capital investment projects include:

  -- Mine development:                                  $6.4 million
  -- Equipment and infrastructure:                 $4.3 million
  -- Tailings dam expansion                           $5.7 million

Non-sustaining investments of $2.8 million relate to improving productivity and
efficiency. Main projects include power transmission capacity upgrade, mill
flotation cells upgrade and pavement of principal mine haulage ways.  These
investments have payback periods ranging between 6 months and 3 years. The
tailings dam expansion allows for additional storage capacity until 2021. 

Lindero gold Project, Argentina

The initial capital cost for the construction of Lindero is estimated at $239
million (see Fortuna news release dated September 21, 2017). For 2018, capital
expenditures are estimated at $201 million, representing 84 % of the
construction budget. 

Project Construction Milestones

Selected milestones from the project construction schedule were released on
December 2017 (see Fortuna news release dated December 21, 2017) and include: 

2018

  -- February: Start mass earthworks
  -- April: First concrete for permanent installations
  -- August: Start of equipment installation, including HPGR tertiary crusher
  -- November: Construction of roads and platforms in preparation for initiation
     of mining activities

2019

  -- January: Commissioning of power plant
  -- March: Placing of first ore on the leach pad
  -- May: First doré poured as part of commissioning

Brownfields Exploration Highlights

San Jose Mine, Mexico

Brownfields exploration program budget for 2018 at the San Jose Mine is $8.4
million, which includes 45,500 meters of diamond drilling and 340 meters of
underground development for drilling access and platforms. Exploration drilling
will focus on the Trinidad Central and Trinidad North zones and on the
sub-parallel Victoria vein. 

Caylloma Mine, Peru

Brownfields exploration program budget for 2018 at the Caylloma Mine is $2.2
million, which includes 10,250 meters of diamond drilling. Drilling will focus
on a previously unexplored area between ore shoots on the Animas NE vein that
were discovered in 2017 (see Fortuna news release dated October 11, 2017). 

Lindero gold Project, Argentina

The Arizaro gold-copper porphyry target lies within the Lindero Project
concession block. We plan to investigate the economic potential of including
Arizaro mineralization into the existing Lindero resource through additional
surface mapping and 2,000 meters of core drilling targeting shallow, high-grade
copper-gold mineralization with a budget of $321,000. 

The Company is also revisiting the extensive reconnaissance exploration
database comprising over fifteen years of sampling and generative work in
northern Argentina, acquired from Goldrock Mines along with the Lindero Project
in 2016. Evaluation of new opportunities on third-party properties is ongoing. 

Greenfields Exploration Highlights

Serbia

Through two C$1.5 million equity investments in Medgold Resources Corp.
(TSX.V:MED), Fortuna funded a Strategic Alliance with Medgold and joint
ventured the Tlamino Project as its first Selected Property (see Medgold news
releases dated January 9, 2017, February 9, 2017, and March 7, 2017). 

Exploration work on the Tlamino joint venture will consist of 2,000 meters of
core drilling with a budget of $340,000. Fortuna retains the right to nominate
a second Selected Property over the course of 2018. Exploration remains
centered on high and low-sulfidation epithermal gold-silver mineralization in
the western portion of the Tethyan orogenic system. Each joint venture, when
formed, will allow Fortuna the right to earn a 51 % interest by spending $3.0
million over three years, and gain an additional 19 % interest by spending a
further $5.0 million and completing a preliminary economic assessment. 

Mexico

Fortuna entered into an equity investment agreement with Prospero Silver Corp.
(TSX.V:PSL) in early 2017 (see Prospero Silver news release dated April 17,
2017). This Strategic Alliance provides for the initial drilling of multiple
targets at Prospero's Matorral, Petate, Pachuca SE and Bermudez properties
located in Durango, Hidalgo and Chihuahua States, respectively. High-level
epithermal clay alteration with anomalous gold, silver or pathfinder elements
are present at each property, none of which has been previously drilled. 

The agreement gives Fortuna the right to select one of the projects to joint
venture with Prospero, potentially earning a 70 % interest by spending $8
million over six years and completing a preliminary economic assessment on the
selected property. Should Fortuna exercise its Prospero warrants, the right to
select a second project under the same terms as above is retained. The
exploration strategy is to complete the planned drilling at all targets, assess
the data and select properties as dictated by the results. 

Drilling at the Matorral and Petate projects was completed in 2017 (see
Prospero Silver news releases dated August 24, 2017, September 18, 2017,
November 8, 2017, and January 10, 2018) and drilling at the Pachuca SE and
Bermudez projects will be completed during the first quarter of 2018. 

Qualified Person

Edwin A. Gutierrez, Technical Services Corporate Manager, is the Qualified
Person for Fortuna Silver Mines Inc. as defined by National Instrument 43-101. 
Mr. Gutierrez is a Registered Member of the Society for Mining, Metallurgy and
Exploration, Inc. (SME Registered Member Number 4119110RM) and is responsible
for ensuring that the information contained in this news release is an accurate
summary of the original reports and data provided to or developed by Fortuna
Silver Mines. 

About Fortuna Silver Mines Inc.

Fortuna is a growth oriented, precious metal producer with its primary assets
being the Caylloma silver mine in southern Peru, the San Jose silver-gold mine
in Mexico and the Lindero gold Project in Argentina.  The company is
selectively pursuing acquisition opportunities throughout the Americas and in
select other areas.  For more information, please visit its website at
www.fortunasilver.com. 

ON BEHALF OF THE BOARD

Jorge A. Ganoza
President, CEO and Director
Fortuna Silver Mines Inc.

Trading symbols: NYSE:FSM | TSX:FVI

Investor Relations:

Carlos Baca- T (Peru): +51.1.616.6060, ext. 0

                           Forward looking Statements

This news release contains forward looking statements which constitute "forward
looking information" within the meaning of applicable Canadian securities
legislation and "forward looking statements" within the meaning of the "safe
harbor" provisions of the Private Securities Litigation Reform Act of 1995
(collectively, "Forward looking Statements"). All statements included herein,
other than statements of historical fact, are Forward looking Statements and
are subject to a variety of known and unknown risks and uncertainties which
could cause actual events or results to differ materially from those reflected
in the Forward looking Statements. The Forward looking Statements in this news
release may include, without limitation, statements about the Company's plans
for its mines and mineral properties, including the Lindero gold Project; the
Company's business strategy, plans and outlook; the merit of the Company's
mines and mineral properties; mineral resource and reserve estimates;
timelines; the future financial or operating performance of the Company;
expenditures; approvals and other matters. Often, but not always, these Forward
looking Statements can be identified by the use of words such as "estimated",
"potential", "open", "future", "assumed", "projected", "used", "detailed", "has
been", "gain", "planned", "reflecting", "will",  "containing", "remaining", "to
be", or statements that events, "could" or "should" occur or be achieved and
similar expressions, including negative variations. 

Forward looking Statements involve known and unknown risks, uncertainties and
other factors which may cause the actual results, performance or achievements
of the Company to be materially different from any results, performance or
achievements expressed or implied by the Forward looking Statements. Such
uncertainties and factors include, among others, whether the Company's
activities at the Lindero gold Project will proceed as planned; changes in
general economic conditions and financial markets; changes in prices for silver
and other metals; technological and operational hazards in Fortuna's mining and
mine development activities; risks inherent in mineral exploration;
uncertainties inherent in the estimation of mineral reserves, mineral
resources, and metal recoveries; governmental and other approvals; political
unrest or instability in countries where Fortuna is active; labor relations
issues; as well as those factors discussed under "Risk Factors" in the
Company's Annual Information Form. Although the Company has attempted to
identify important factors that could cause actual actions, events or results
to differ materially from those described in Forward looking Statements, there
may be other factors that cause actions, events or results to differ from those
anticipated, estimated or intended. 

Forward looking Statements contained herein are based on the assumptions,
beliefs, expectations and opinions of management, including but not limited to:
that the Company's activities at the Lindero gold Project will proceed as
planned; expectations regarding mine production costs; expected trends in
mineral prices and currency exchange rates; the accuracy of the Company's
current mineral resource and reserve estimates; that the Company's activities
will be in accordance with the Company's public statements and stated goals;
that there will be no material adverse change affecting the Company or its
properties; that all required approvals will be obtained; that there will be no
significant disruptions affecting operations and such other assumptions as set
out herein. Forward looking Statements are made as of the date hereof and the
Company disclaims any obligation to update any Forward looking Statements,
whether as a result of new information, future events or results or otherwise,
except as required by law. There can be no assurance that Forward looking
Statements will prove to be accurate, as actual results and future events could
differ materially from those anticipated in such statements. Accordingly,
investors should not place undue reliance on Forward looking Statements. 

This news release also refers to non-GAAP financial measures, such as cash cost
per tonne of processed ore; cash cost per payable ounce of silver; total
production cost per tonne; all-in sustaining cash cost; all-in cash cost;
adjusted net (loss) income; operating cash flow per share before changes in
working capital, income taxes, and interest income; and adjusted EBITDA. These
measures do not have a standardized meaning or method of calculation, even
though the descriptions of such measures may be similar. These performance
measures have no meaning under International Financial Reporting Standards
(IFRS) and therefore, amounts presented may not be comparable to similar data
presented by other mining companies. 

                                                                        Appendix

                          2018 AISC Guidance Breakdown

San Jose Mine:

                Item                  $/oz Ag
Cash cost net of by-product credits     1.4  
Commercial and government royalties/    1.2  
mining tax                                   
Workers' participation                  0.9  
Subsidiary G&A                          0.7  
Sustaining capex                        1.2  
Brownfields exploration                 1.2  
AISC                                    6.6  

Caylloma Mine:

                Item                   $/oz Ag
Cash cost net of by-product credits   (40.3  )
Commercial and government royalties/    4.1   
mining tax                                    
Workers' participation                  2.4   
Subsidiary G&A                          4.7   
Sustaining capex                       21.1   
Brownfields exploration                 2.8   
AISC                                   (5.2  )

Consolidated:

                Item                  $/oz Ag
Cash cost net of by-product credits   (2.7  )
Commercial and government royalties/   1.5   
mining tax                                   
Workers' participation                 1.1   
Subsidiary G&A                         1.1   
Corporate G&A                          1.4   
Sustaining capex                       3.1   
Brownfields exploration                1.3   
AISC                                   6.8   

Note: Total figures may not add up due to rounding
Großer Insider-Report 2024 von Dr. Dennis Riedl
Wenn Insider handeln, sollten Sie aufmerksam werden. In diesem kostenlosen Report erfahren Sie, welche Aktien Sie im Moment im Blick behalten und von welchen Sie lieber die Finger lassen sollten.
Hier klicken
© 2018 GlobeNewswire
Werbehinweise: Die Billigung des Basisprospekts durch die BaFin ist nicht als ihre Befürwortung der angebotenen Wertpapiere zu verstehen. Wir empfehlen Interessenten und potenziellen Anlegern den Basisprospekt und die Endgültigen Bedingungen zu lesen, bevor sie eine Anlageentscheidung treffen, um sich möglichst umfassend zu informieren, insbesondere über die potenziellen Risiken und Chancen des Wertpapiers. Sie sind im Begriff, ein Produkt zu erwerben, das nicht einfach ist und schwer zu verstehen sein kann.