Sept 10 (Reuters) - High River Gold Mines Ltd:
* Reports feasibility study results for the Bissa Gold Project
* Says probable reserves estimated at 703,655 ounces
* Says average annual gold production of approximately 95,000 ounces
* Says expects to receive exploitation permit for bissa project in Q4 2010
((Bangalore Equities Newsroom; +91 80 4135 5800; within U.S. +1 646 223 8780))
(For more news, please click here) COPYRIGHT Copyright Thomson Reuters 2010. All rights reserved. The copying, republication or redistribution of Reuters News Content, including by framing or similar means, is expressly prohibited without the prior written consent of Thomson Reuters.
* Reports feasibility study results for the Bissa Gold Project
* Says probable reserves estimated at 703,655 ounces
* Says average annual gold production of approximately 95,000 ounces
* Says expects to receive exploitation permit for bissa project in Q4 2010
((Bangalore Equities Newsroom; +91 80 4135 5800; within U.S. +1 646 223 8780))
(For more news, please click here) COPYRIGHT Copyright Thomson Reuters 2010. All rights reserved. The copying, republication or redistribution of Reuters News Content, including by framing or similar means, is expressly prohibited without the prior written consent of Thomson Reuters.