Dec 23 (Reuters) - A-Power Energy Generation Systems Ltd:
* Announces epc contract with inner Mongolia Huolinhe Coal Trade Group Co.,
Ltd., for a 4x200 mw micro grid project
* Says project is expected to be fully operational by December 31, 2015
* Project includes four 1048 t/h circulating fluidized bed boilers with 4 200
megawatt turbine power generators
* Says total investment for the project is expected to be about $597 million
((Bangalore Equities Newsroom; +91 80 4135 5800; within U.S. +1 646 223 8780)) (For more news, please click here) COPYRIGHT Copyright Thomson Reuters 2010. All rights reserved. The copying, republication or redistribution of Reuters News Content, including by framing or similar means, is expressly prohibited without the prior written consent of Thomson Reuters.
* Announces epc contract with inner Mongolia Huolinhe Coal Trade Group Co.,
Ltd., for a 4x200 mw micro grid project
* Says project is expected to be fully operational by December 31, 2015
* Project includes four 1048 t/h circulating fluidized bed boilers with 4 200
megawatt turbine power generators
* Says total investment for the project is expected to be about $597 million
((Bangalore Equities Newsroom; +91 80 4135 5800; within U.S. +1 646 223 8780)) (For more news, please click here) COPYRIGHT Copyright Thomson Reuters 2010. All rights reserved. The copying, republication or redistribution of Reuters News Content, including by framing or similar means, is expressly prohibited without the prior written consent of Thomson Reuters.
© 2010 AFX News