Anzeige
Mehr »
Login
Freitag, 19.04.2024 Börsentäglich über 12.000 News von 689 internationalen Medien
Goldaktie: Eine Erfolgsgeschichte, die seinesgleichen sucht, startet gerade richtig durch!
Anzeige

Indizes

Kurs

%
News
24 h / 7 T
Aufrufe
7 Tage

Aktien

Kurs

%
News
24 h / 7 T
Aufrufe
7 Tage

Xetra-Orderbuch

Fonds

Kurs

%

Devisen

Kurs

%

Rohstoffe

Kurs

%

Themen

Kurs

%

Erweiterte Suche
Marketwired
211 Leser
Artikel bewerten:
(0)

Benton Resources Notified of Revisions to the Positive PEA for the Cape Ray Gold Project, Newfoundland

THUNDER BAY, ONTARIO -- (Marketwired) -- 03/31/17 -- Benton Resources Inc. (TSX VENTURE: BEX) ("Benton" or "the Company") has received updated numbers from its joint venture partner Nordmin Engineering Ltd. ("Nordmin") regarding the preliminary economic assessment ("PEA") announced February 9, 2017. Nordmin reports that during the independent review process, an error in the interpretation of the 2017 resource block model for the underground portion of the 51 Zone at the Cape Ray Gold Project was discovered. Due to the error, the ounces of gold for the underground portion of the 51 Deposit were overstated and as a result, the 51 Underground Zone is marginally economic and has been removed from the PEA. The Internal Rate of Return (IRR) and Net Present Value (NPV) for the updated PEA have subsequently been reduced until economic parameters change. The IRR and NPV@7% remain higher than the 2016 PEA and the updated PEA continues to demonstrate the economic potential of the Cape Ray Project. A substantial review of the entire updated PEA was initiated and the new results form the basis of this press release. The Cape Ray Gold Project, is located approximately 20 kilometers northeast of Port aux Basques, Newfoundland.

The revised updated results of the PEA include a pre-tax net present value NPV at 7% of $48.5 million with a pre-tax IRR of 31 percent and a post-tax NPV at a 7 percent discount rate of $32.4 million with a post-tax IRR of 25 percent.

The 2016 drilling program provided the team with numerous insights into the nature of this project. It allowed the team to revise the geologic and resource models to better represent the intrinsic nature of the mineral resource, and make a re-assessment to the overall approach and layout of the proposed mine design. The PEA is based on the mineral resource estimate completed by Ginto Consulting Inc., outlined in the National Instrument 43-101 technical report update.

Highlights from the PEA, with the base-case gold price of $1,306 (U.S.) per ounce and an exchange rate of $1.26 CAD/USD, are as follows (all figures in Canadian dollars unless otherwise stated):

--  Pre-production Capital is $58.2 million with a contingency of 10%
    included within the initial capital. Pre-production is for a 2 year
    period.
--  Sustaining Capital of $12.8 million with a 5% contingency for the Life
    of Mine.
--  Pre-tax NPV (7%) of $48.5 million and internal rate of return of 31%.
--  Post-tax NPV (7%) of $32.4 million and internal rate of return of 25%.
--  Net Revenue of $397.5 million over 9 year LOM.
--  Positive Cash-flow is realized in year 2.
--  2.9 million tonnes of mill feed averaging 2.5 g/t gold and 8.1 g/t
    silver.
--  The mill operates at an average rate of 1,000 tonnes per day.
--  Total production of 234,851 ounces of gold and 483,383 ounces of silver.
--  Gold recovery of 98% and Silver recovery 63%.

All of the economics are completed on Indicated and Inferred categories of the mineral resource model. The comparison from last year's PEA has shown an increase in indicated mineral resource.

--------------------------------------------------
                                                Pre-Tax
----------------------------------------------------------------------------
           Year                      2017                     2016
----------------------------------------------------------------------------
            IRR                      31%                      29%
----------------------------------------------------------------------------
       Discount rate                        NPV ($ million)
----------------------------------------------------------------------------
            0%                       84.2                     88.4
----------------------------------------------------------------------------
            7%                       48.5                     48.4
----------------------------------------------------------------------------
            10%                      37.7                     36.7
----------------------------------------------------------------------------
            15%                       24                       22
----------------------------------------------------------------------------
                                               After Tax
----------------------------------------------------------------------------
            IRR                      25%                      24%
----------------------------------------------------------------------------
       Discount rate                        NPV ($ million)
----------------------------------------------------------------------------
            0%                       59.8                     63.4
----------------------------------------------------------------------------
            7%                       32.4                     32.6
----------------------------------------------------------------------------
            10%                      24.1                     23.6
----------------------------------------------------------------------------
            15%                      13.5                     12.3
----------------------------------------------------------------------------

Mineral Resources - Effective date of February 1, 2017

----------------------------------------------------------------------------
51 ZONE + 04 ZONE + 41 ZONE+WGH - INDICATED MINERAL RESOURCES (1,2,3)
----------------------------------------------------------------------------
Au Cut-Off  Tonnage  Average Au   Total Au oz.  Average Ag     Total Ag oz.
   (g/t)     (,000)     (g/t)        (,000)        (g/t)          (,000)
----------------------------------------------------------------------------
    1.0      4,148       2.75          367          9.76          1,302
----------------------------------------------------------------------------
    1.5      2,783       3.50          313         11.67          1,045
----------------------------------------------------------------------------
    2.0      1,990       4.21          269         13.13           840
----------------------------------------------------------------------------
    2.5      1,486       4.87          233         14.71           703
----------------------------------------------------------------------------
    3.0      1,155       5.49          204         16.14           599
----------------------------------------------------------------------------
    3.5       928        6.03          180         17.26           515
----------------------------------------------------------------------------
    4.0       754        6.57          159         18.15           440
----------------------------------------------------------------------------
    4.5       621        7.06          141         19.12           382
----------------------------------------------------------------------------
    5.0       512        7.56          124         20.10           331
----------------------------------------------------------------------------

----------------------------------------------------------------------------
51 ZONE + 04 ZONE + 41 ZONE + WGH ZONE - INFERRED MINERAL RESOURCES (1,2,3)
----------------------------------------------------------------------------
 Au Cut-Off Tonnage  Average Au   Total Au oz.  Average Ag     Total Ag oz.
    (g/t)    (,000)     (g/t)        (,000)        (g/t)          (,000)
----------------------------------------------------------------------------
    1.0      2,770       1.77          158          6.57           585
----------------------------------------------------------------------------
    1.5      1,199       2.54          98           9.22           355
----------------------------------------------------------------------------
    2.0       725        3.07          72          10.46           244
----------------------------------------------------------------------------
    2.5       357        3.99          46          13.22           152
----------------------------------------------------------------------------
    3.0       204        4.95          32          15.70           103
----------------------------------------------------------------------------
    3.5       144        5.65          26          15.32            71
----------------------------------------------------------------------------
    4.0       105        6.38          21          15.83            53
----------------------------------------------------------------------------
    4.5        96        6.59          20          16.06            49
----------------------------------------------------------------------------
    5.0        77        7.03          18          16.34            41
----------------------------------------------------------------------------

1.  Mineral Resources are not Mineral Reserves and do not have demonstrated
    economic viability. There is no certainty that all or any part of the
    Mineral Resources estimated will be converted into Mineral Reserves. The
    estimate of Mineral Resources may be materially affected by
    environmental, permitting, legal, title, taxation, socio-political,
    marketing, or other relevant issues.
2.  The CIM definitions were followed for the classification of Measured,
    Indicated, and Inferred mineral resources.
3.  The quantity and grade of reported Inferred Resources in this estimation
    are uncertain in nature and there has been insufficient exploration to
    define these Inferred Resources as an Indicated or Measured Mineral
    Resource and it is reasonably expected that a portion of inferred
    mineral resources could be upgraded with continued exploration

"The revised results continue to support the economic potential of the Cape Ray Gold Project," stated Stephen Stares, President and CEO of Benton. "We see numerous opportunities to further enhance the economics through additional studies and exploration with a high probability for resource expansion and good potential for new discoveries across the property. We will now focus on advancing the Cape Ray project toward feasibility through additional exploration, environmental permitting and further studies." Benton recognizes that this is an undeveloped area of Newfoundland. As such, protecting the environment is of great importance. To facilitate the development of a sustainable project, Nordmin, the joint partner, has experts on staff to complete the necessary studies required concerning environmental monitoring, assessment and permitting matters.

The Company has initiated work towards firming up costs and preparing a prefeasibility study. Apart from further metallurgical studies, the work will include drilling and tailings characterization as well as environmental baseline studies, hydrology monitoring, flora and fauna studies. A NI 43-101 technical report for Cape Ray PEA will be filed on SEDAR (www.sedar.com).

The reader should be cautioned that the PEA is preliminary in nature. It contains inferred mineral resources that are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves. There is no certainty that the results of the PEA will be realized.

Cape Ray combined open-pit and underground mine

Key economic assumptions and results

----------------------------------------------------------------------------
Description                                        Units          Value
----------------------------------------------------------------------------
Total mineralized rock mined                        Kt.            2,94
----------------------------------------------------------------------------
Gold grade                                          g/t            2.53
----------------------------------------------------------------------------
Silver grade                                        g/t            8.10
----------------------------------------------------------------------------
AuEq grade                                          g/t            2.65
----------------------------------------------------------------------------
Gold recovery                                        %              98
----------------------------------------------------------------------------
Silver recovery                                      %              63
----------------------------------------------------------------------------
Gold price                                        US$/oz.        1,306.15
----------------------------------------------------------------------------
Silver price                                      US$/oz.         18.97
----------------------------------------------------------------------------
Exchange Rate $USD/$CAD                                           1.262
----------------------------------------------------------------------------
Payable gold metal                                  oz.          234,851
----------------------------------------------------------------------------
Payable silver metal                                oz.          483,383
----------------------------------------------------------------------------
Total net revenue                                $ million        397.5
----------------------------------------------------------------------------
Total capital costs (Project and Sustaining)     $ million         71.0
----------------------------------------------------------------------------
Overall Operating costs (total)                  $ million        242.3
----------------------------------------------------------------------------
Overall Operating cost (AuEq)                    US$/ozAuEq       767.1
----------------------------------------------------------------------------
(AISC) Overall cost (AuEq)                       US$/ozAuEq       991.9
----------------------------------------------------------------------------
Payback period                                     years            2
----------------------------------------------------------------------------
Mine Life                                          years            9
----------------------------------------------------------------------------
Pre-tax Cumulative net cash flow                 $ million         84.2
----------------------------------------------------------------------------
Post-tax Cumulative net cash flow                $ million         59.8
----------------------------------------------------------------------------
Pre - tax NPV (7%)                               $ million         48.5
----------------------------------------------------------------------------
Pre - tax IRR                                        %              31
----------------------------------------------------------------------------
Post - tax NPV (7%)                              $ million         32.4
----------------------------------------------------------------------------
Post - tax IRR                                       %              25
----------------------------------------------------------------------------

Capital and operating costs

The Cape Ray Project has been envisioned as an open-pit mine with starter pits for all the zones and one underground mining operation at the 04 zone. Open-pit and underground mining are anticipated to be completed by contract mining companies. The equipment will be supplied by the contractor that is awarded the work.

Grid electrical power will provide the majority of the electrical power to the project over the life of the mine. The work force is expected to come from the Isle aux Morts area for the operation of the Mill. The rest of the workforce will be the responsibility of the contractor.

Total capital cost estimate

----------------------------------------------------------------------------
Capital Expenditures                            Contingency     $ million
----------------------------------------------------------------------------
Sustaining Capital Expenditures by Zone
----------------------------------------------------------------------------
    PIT 41                                           5%             -
----------------------------------------------------------------------------
    PIT 51                                           5%             -
----------------------------------------------------------------------------
    PIT 04                                           5%             -
----------------------------------------------------------------------------
    Window Glass                                     5%            2.89
----------------------------------------------------------------------------
    U.G. 04                                          5%            9.93
----------------------------------------------------------------------------
Permitting                                          10%            2.17
----------------------------------------------------------------------------
Road work (Quote from Adams Construction)           10%            3.53
----------------------------------------------------------------------------
Overburden Removal                                  10%            1.07
----------------------------------------------------------------------------
Surface Infrastructure - General                    10%            2.84
----------------------------------------------------------------------------
Ore and Waste Pads (3) - Mine & Mill                10%            0.44
----------------------------------------------------------------------------
Surface Shop                                        10%            1.68
----------------------------------------------------------------------------
Land Costs                                          10%            0.91
----------------------------------------------------------------------------
Mill Capital                                        10%           33.18
----------------------------------------------------------------------------
Tailings                                            10%            3.82
----------------------------------------------------------------------------
Water Treatment Plants / Testing                    10%            0.56
----------------------------------------------------------------------------
Power Distribution to Mill                          10%            1.16
----------------------------------------------------------------------------
Working Capital                                     10%            0.84
----------------------------------------------------------------------------
Engineering for Capital                             10%            1.17
----------------------------------------------------------------------------
OH & In-directs                                     10%            1.00
----------------------------------------------------------------------------
Mine Closure                                         0%            3.82
----------------------------------------------------------------------------
Total Capital Expenditures                                        71.00
----------------------------------------------------------------------------

Production and Processing

Operations for the Cape Ray project is planned to have both Open Pit and Underground Mining. Each zone will be campaigned separately with the use of contractors. The initial mill feed will come from the 04 zone open pit. Once the 04 pit is completed the 51 pit will commence to be mined and the underground contractor will set up, drive the decline and levels and begin long-hole mining. This implies the UG contractor is going to mine 51 UG? The start of the Window Glass pit will begin once the 41 pit is mined. All the zones combined will give a current mine life of 9 years at a milling through-put of 1,000 tonnes per day. The process plant includes conventional crushing, grinding, gravity, and whole ore cyanide leach. A gold and silver dore will be produced on site. Process reagents will be removed from the plant tailings prior to placement in a tailings management facility.

----------------------------------------------------------------------------
Mineral Resources                     Avg. Au       Avg. Ag       Tonnes
                                        g/t           g/t         (,000)
----------------------------------------------------------------------------
Pit 41                                 2.06          7.46           630
----------------------------------------------------------------------------
PIT 51                                 4.17          12.97          475
----------------------------------------------------------------------------
PIT 04                                 4.39          10.55          270
----------------------------------------------------------------------------
Window Glass                           1.50          5.39          1,414
----------------------------------------------------------------------------
U.G. 04                                 5.6          16.43          151
----------------------------------------------------------------------------
Stockpile                               7.5          16.43           3
----------------------------------------------------------------------------
Total                                                              2,943
----------------------------------------------------------------------------

The mill feed tonnes in the mine plan include Inferred Mineral Resources. The reader is cautioned that Inferred Mineral Resources are considered too speculative geologically to have economic considerations applied to them that would enable categorization as Mineral Reserves. There is no certainty that Inferred Mineral Resources will ever be upgraded to Reserves. Mineral Resources that are not Mineral Reserves do not have demonstrated economic viability.

Going forward, the team will be working on laying out the next 5000 meter drilling program that will commence this summer, which will also include some geotechnical drilling to support the pit designs and other work on site and continue to work towards environmental milestones to progress the project to the next phase.

Qualified Persons and 43-101 Disclosure:

Marc Jutras, P.Eng., M.A.Sc., Principal, Mineral Resources, at Ginto Consulting Inc. is an independent Qualified Person as per National Instrument 43-101, and is responsible for the estimation of Cape Ray's mineral resources. Mr. Jutras has reviewed and verified that the technical information related to the estimation of the mineral resources contained herein is accurate and approves of the written disclosure of same.

Mike Petrina P.Eng Principal Mining Engineer Moose Mountain Technical Services is an independent Qualified Person as per National Instrument 43-101, and has reviewed the mine plan, production schedule, operating and capital costs and approves the written disclosure of same.

About Benton Resources Inc. (TSX VENTURE: BEX)

Benton Resources Inc. is a well-funded Canadian-based junior with a diversified property portfolio in Gold-Silver, Nickel, Copper, and Platinum group elements.

Clinton Barr (P.Geo.), V.P. Exploration for Benton Resources Inc., is the qualified person responsible for this release has prepared, supervised the preparation or approved the scientific and technical disclosure in the news release.

On behalf of the Board of Directors of Benton Resources Inc.,

Stephen Stares, President

THE TSX VENTURE EXCHANGE HAS NOT REVIEWED AND DOES NOT ACCEPT RESPONSIBILITY FOR THE ADEQUACY OR ACCURACY OF THIS RELEASE.

The information contained herein contains "forward-looking statements" within the meaning of applicable securities legislation. Forward-looking statements relate to information that is based on assumptions of management, forecasts of future results, and estimates of amounts not yet determinable. Any statements that express predictions, expectations, beliefs, plans, projections, objectives, assumptions or future events or performance are not statements of historical fact and may be "forward-looking statements."

Forward-looking statements are subject to a variety of risks and uncertainties which could cause actual events or results to differ from those reflected in the forward-looking statements, including, without limitation: risks related to failure to obtain adequate financing on a timely basis and on acceptable terms; risks related to the outcome of legal proceedings; political and regulatory risks associated with mining and exploration; risks related to the maintenance of stock exchange listings; risks related to environmental regulation and liability; the potential for delays in exploration or development activities or the completion of feasibility studies; the uncertainty of profitability; risks and uncertainties relating to the interpretation of drill results, the geology, grade and continuity of mineral deposits; risks related to the inherent uncertainty of production and cost estimates and the potential for unexpected costs and expenses; results of prefeasibility and feasibility studies, and the possibility that future exploration, development or mining results will not be consistent with the Company's expectations; risks related to gold price and other commodity price fluctuations; and other risks and uncertainties related to the Company's prospects, properties and business detailed elsewhere in the Company's disclosure record. Should one or more of these risks and uncertainties materialize, or should underlying assumptions prove incorrect, actual results may vary materially from those described in forward-looking statements. Investors are cautioned against attributing undue certainty to forward-looking statements. These forward looking statements are made as of the date hereof and the Company does not assume any obligation to update or revise them to reflect new events or circumstances. Actual events or results could differ materially from the Company's expectations or projections.

Contacts:
Stephen Stares
684 Squier Street
Thunder Bay, ON P7B 4A8
Phone (807) 475-7474
Fax (807) 475-7200
www.bentonresources.ca

Großer Insider-Report 2024 von Dr. Dennis Riedl
Wenn Insider handeln, sollten Sie aufmerksam werden. In diesem kostenlosen Report erfahren Sie, welche Aktien Sie im Moment im Blick behalten und von welchen Sie lieber die Finger lassen sollten.
Hier klicken
© 2017 Marketwired
Werbehinweise: Die Billigung des Basisprospekts durch die BaFin ist nicht als ihre Befürwortung der angebotenen Wertpapiere zu verstehen. Wir empfehlen Interessenten und potenziellen Anlegern den Basisprospekt und die Endgültigen Bedingungen zu lesen, bevor sie eine Anlageentscheidung treffen, um sich möglichst umfassend zu informieren, insbesondere über die potenziellen Risiken und Chancen des Wertpapiers. Sie sind im Begriff, ein Produkt zu erwerben, das nicht einfach ist und schwer zu verstehen sein kann.