In its September quarterly report, BCI reported that the definitive feasibility study (DFS) on the Mardie salt and potash project was 75% complete as at end-September 2019, with the expectation that it will be completed in Q1 CY20. In the meantime, the company is embarking on construction of a large-scale trial pond programme to test the envisaged materials and methods of construction and thereby substantially mitigate future construction risk.Den vollständigen Artikel lesen ...