DJ Genel Energy PLC: Trading and operations update
Genel Energy PLC (GENL)
Genel Energy PLC: Trading and operations update
03-Nov-2020 / 07:00 GMT/BST
Dissemination of a Regulatory Announcement that contains inside information
according to REGULATION (EU) No 596/2014 (MAR), transmitted by EQS Group.
The issuer is solely responsible for the content of this announcement.
3 November 2020
Genel Energy plc
Trading and operations update
Genel Energy plc ('Genel' or 'the Company') issues the following trading and
operations update in respect of the third quarter and first nine months of
2020.
Bill Higgs, Chief Executive of Genel, said:
"Genel continues to demonstrate its resilience and ability to be move
quickly to navigate changing external conditions. Production has remained
robust, increasing quarter on quarter, and first oil at Sarta is also now
imminent. Once production from these initial wells has stabilised we expect
it to increase our production by over 10%, with potentially far more to come
as we appraise what could be the largest field in the Kurdistan Region of
Iraq.
Following the successful completion of our recent refinancing, we have the
liquidity to fund the rapid development of Sarta in the case of appraisal
success in 2021. Genel's financial strength and disciplined capital
allocation means it is well placed to pursue opportunities for value
accretive growth and provide returns to shareholders."
FINANCIAL PERFORMANCE
· $142 million of cash proceeds received in the first nine months of 2020
· Free cash flow outflow of $5 million in the first nine months of 2020,
after $30 million of capital expenditure progressing pre-production
assets, and total capital expenditure of $76 million
· $145 million outstanding from the Kurdistan Regional Government
('KRG'), of which $121 million owed for production from November 2019 to
February 2020, and $24 million in suspended override payments
· Cash of $341 million at 30 September 2020 ($355 million at 30 June 2020)
· Net cash of $42 million at 30 September 2020 ($57 million at 30 June
2020)
· Cash figures are stated prior to the successful completion of
refinancing in October 2020
· Interim dividend of 5¢ per share (2019: 5¢ per share), a distribution of
c.$13.6 million, to be paid to shareholders on the register on 13 November
2020
REFINANCING AND FINANCIAL STRATEGY
· In September 2020, Genel successfully completed the issuance of a new
$300 million senior unsecured bond with maturity in October 2025. The new
bond has a fixed coupon of 9.25% per annum, compared to 10% for the 2022
bonds
· At the same time, Genel purchased $223 million of its 2022 bonds at
107 to par. The total cost incurred with the redemption of these bonds
was $16 million
· Following the successful refinancing, the Company therefore has $77
million of 2022 bonds and $300 million of 2025 bonds in issue
· Genel remains committed to retaining a robust balance sheet, and the
successful completion of the bond issuance has allowed Genel to
significantly extend its liquidity runway and provides the foundation for
a capital investment programme that is flexible and adaptable to the
external environment
· The right level of debt and the resulting liquidity remains under review
in the context of planned investment activity, external market conditions
and the recovery of KRG receivables, the Company retaining the option of
holding an optimised combination of the old and/or new bonds, depending on
availability and pricing
OPERATING PERFORMANCE
· Net production averaged 32,140 bopd in the first nine months of 2020,
with net production in Q3 averaging 32,210 bopd (Q2 2020: 30,040 bopd)
· Production by field was as follows:
(bopd) Gross production Net production
Q3 2020 Q3 2020
Tawke 56,880 14,220
Peshkabir 56,860 14,210
Taq Taq 8,580 3,780
Total 122,320 32,210
PRODUCTION ASSETS
· Tawke PSC (25% working interest)
· Production at the Tawke PSC increased to 113,700 bopd in the third
quarter, up 12% from the prior quarter following a campaign of quick
turnaround, low-cost well interventions and the start-up of the
Kurdistan Region of Iraq's first enhanced oil recovery project
· The Peshkabir-to-Tawke gas capture and reinjection project, in
operation since mid-year, is continuing to cut gas flaring and
greenhouse emissions by half at Peshkabir to 7kg CO2e/bbl, while
unlocking additional oil at Tawke. By the end of October 2020, two
billion cubic feet of gas that otherwise would have been flared had been
injected into Tawke, already delivering a positive production response
at the field, and at the same time reducing field water production
· Taq Taq PSC (44% working interest and joint operator)
· Taq Taq gross field production averaged 8,580 bopd in Q3, following
the suspension of drilling activity in H1 2020
· As previously stated, activity at Taq Taq is focused on optimising
cash flow. Appropriate for the external environment, it is not expected
that there will be any further drilling activity in 2020
PRE-PRODUCTION ASSETS
· Sarta (30% working interest)
· Despite the challenges of COVID-19, first oil is on track for Q4 2020
· Production will initially be from the Sarta-2 and Sarta-3 wells, and
the workover of the former is now underway. It is expected that a stable
production level will be reached in Q1 2021
· Preparations for the 2021 appraisal drilling campaign, which is
targeting a material portion of the 250 MMbbls of contingent resources
in the Jurassic, are ongoing
· This appraisal campaign will begin with the Sarta-6 well in H1 2021,
followed by the Sarta-5 well and Sarta-1D re-entry. Well pad and road
access civil works are well underway at both the Sarta-6 and Sarta-5
locations, and minor remedial civil works are also about to commence at
the existing Sarta-1D site. It is expected that all three appraisal
wells will complete in 2021, at a cost of c.$40 million net to Genel in
2021
· Qara Dagh (40% working interest and operator)
· While challenges caused by COVID-19 remain, the increased certainty in
the operating environment, and Genel's ability to operate under the
expected level of restrictions, has allowed the lifting of force majeure
at Qara Dagh
· This has allowed Genel to proceed with approvals for activities
necessary in order to reach a spud date for the QD-2 well in Q1 2021
· The QD-2 well is expected to cost c.$30 million in 2021
· Bina Bawi (100% working interest and operator)
· Genel continues to seek a response from the KRG to our proposal
submitted in August 2020, which would enable the Company to progress the
next stage of activity at Bina Bawi
· Our proposal highlights the need to engage regional gas buyers on
volume and price discovery and to improve project definition by
undertaking the detailed front-end engineering of both the upstream and
midstream processing facilities
· Until a satisfactory response is received, Genel will maintain capex
discipline, and will only commence investment upon certainty of
alignment with the KRG and a clear path to monetisation
· African exploration assets
· The uncertainty created by COVID-19, and current macroeconomic
conditions, has negatively impacted the search for partners to fund and
minimise Genel's spend on our potentially high-impact exploration wells
· A farm-out process relating to the highly prospective SL10B13 block in
Somaliland (100% working interest and operator) is however continuing,
with companies still assessing the opportunity
· A farm-out campaign is being planned relating to the Lagzira block
offshore Morocco (75% working interest and operator), with the aim of
bringing a partner onto the licence prior to considering further
commitments
ESG
· Zero lost time injuries ('LTI') and zero tier one losses of primary
containment in 2020 to date at Genel and TTOPCO operations
· There has not been an LTI since 2015, with almost 13 million work
hours since the last incident
· Carbon intensity of our portfolio now reduced to 7kg CO2e/bbl of scope 1
and 2 emissions following material reduction in flaring at the Tawke PSC
through completion and commissioning of the enhanced oil recovery project
· Multiple projects are ongoing to support local communities in the
Kurdistan Region of Iraq, and the pipeline project to transport clean
water to over 220 families across five villages neighbouring Taq Taq is
now complete
· Sustainability report in accordance with Global Reporting Initiative
standards was issued in September 2020, giving a comprehensive overview of
our ESG activities and positions, noting the impact we have had on the
Kurdistan Region of Iraq ('KRI'):
· Since starting work in the KRI Genel has invested c.$60 million in
social projects, and $36 million spent on contracts with local companies
· 245 social investment and community projects funded and successfully
delivered
· Up to 550 local community patients receive free treatment from the
TTOPCO medical team per year
· 250 local people employed at TTOPCO, and 23 local community-centred
companies are providing services to Genel's operations across the KRI,
with our operations indirectly supporting a further 350 local people
through such contracts
OUTLOOK
(MORE TO FOLLOW) Dow Jones Newswires
November 03, 2020 02:00 ET (07:00 GMT)
© 2020 Dow Jones News