- (PLX AI) - EDF says Hinkley Point C start of electricity generation for Unit 1 is targeted for June 2027.
- • EDF Hinkley Point C risk of further delay of the two units is assessed at 15 months
- • EDF Hinkley Point C project completion costs are now estimated in the range of £25Bn to £26Bn