Anzeige
Mehr »
Freitag, 09.01.2026 - Börsentäglich über 12.000 News
Fundamental stark, Kurs zu niedrig - Chance beim Krebs-Impfstoff-Pionier!
Anzeige

Indizes

Kurs

%
News
24 h / 7 T
Aufrufe
7 Tage

Aktien

Kurs

%
News
24 h / 7 T
Aufrufe
7 Tage

Xetra-Orderbuch

Fonds

Kurs

%

Devisen

Kurs

%

Rohstoffe

Kurs

%

Themen

Kurs

%

Erweiterte Suche

WKN: A2N4CD | ISIN: AU0000021461 | Ticker-Symbol: 9CH
Tradegate
09.01.26 | 10:24
0,210 Euro
-0,95 % -0,002
Branche
Rohstoffe
Aktienmarkt
AUSTRALIEN
1-Jahres-Chart
GALAN LITHIUM LIMITED Chart 1 Jahr
5-Tage-Chart
GALAN LITHIUM LIMITED 5-Tage-Chart
RealtimeGeldBriefZeit
0,1990,20910:30
0,2020,21010:31
ACCESS Newswire
472 Leser
Artikel bewerten:
(2)

Galan Lithium Limited: HMW Plant in Transit to Site, Phase 1 on Track

Highlights:

  • Nano-filtration plant has been assembled and tested off-site and is now in transit to Hombre Muerto West (HMW)

  • Phase 1 construction activities at HMW continue to advance toward completion, ahead of expected first production of lithium chloride in H1 2026

PERTH, AU / ACCESS Newswire / December 15, 2025 / Galan Lithium Limited (ASX:GLN) (Galan or the Company) is pleased to provide an update on the progress of its Phase 1 construction activities for HMW, as it advances towards its final stages.

Nano-Filtration Plant

Significant progress has been achieved on the nano-filtration plant, a critical component of the Phase 1 operation. In Sydney, general assembly of the nano-filtration plant has been completed, and pre-installation testing of the plant has also been successfully completed.

The nano-filtration plant is now in transit and is expected to arrive in South America in early 2026. Commissioning activities will commence immediately following the plant's arrival at the HMW site.

Figure 1. Load out of part of the nano-filtration plant

Figure 2. Nano-filtration pumping units loaded into containers for transport

Evaporation Ponds and Site Works

At HMW, evaporation Ponds 4 and 5 have been re-designed and scaled to support the Phase 1 production rate of 4,000 tonnes per annum of lithium carbonate equivalent ("LCE"). Liner installation on Pond 4 and 5 has been completed, and works are currently underway to subdivide areas of these ponds to optimize the concentration process of the lithium chloride product.

Figure 3. Liner installation team working on pond 4

Figure 4. Liner installation for ponds 4 and 5, adjacent to ponds 1-3.

Earthworks at the plant area have been completed, and the concrete foundation for the processing plant has been poured.

Key project infrastructure items, including power supply, electrical systems and pumps, have been ordered or procured in line with the Phase 1 construction schedule. Phase 1 of the HMW Project remains on track to be delivered within budget, with construction and procurement activities progressing in accordance with the Company's development plan.

The Company has also started to evaluate an option to expand the production capacity of Phase 1 HMW (4,000 tpa LCE) to the original Phase 1 capacity (around 5,400 tpa LCE) as studied in the 2023 HMW Phase 1 Definitive Feasibility Study.

Figure 5. Foundations for HMW plant site

Galan's Managing Director, Juan Pablo (JP) Vargas de la Vega, commented:

"Solid progress at Hombre Muerto West continues to reflect the strong commitment and teamwork of our entire team as well as our contractors and partners at Authium Ltd. Completing assembly and testing of the nano-filtration plant and advancing site works at HMW are important milestones as we move closer to first production. The project is transitioning into an exciting final phase of construction and commissioning. The momentum being built across the team gives us confidence as we move toward becoming a producing lithium company."

The Galan Board has authorised this release.

For further information contact:

COMPANY

Juan Pablo ("JP") Vargas de la Vega
Managing Director
jp@galanlithium.com.au
+ 61 8 9214 2150

MEDIA

Matt Worner
Vector Advisors
mworner@vectoradvisors.au
+61 429 522 924

SOURCE: Galan Lithium Limited



View the original press release on ACCESS Newswire:
https://www.accessnewswire.com/newsroom/en/metals-and-mining/hmw-plant-in-transit-to-site-phase-1-on-track-1117328

© 2025 ACCESS Newswire
Renditeturbo 2026 - 5 Aktien mit Potenzial
2025 neigt sich dem Ende zu, ohne klassische Jahresendrallye, aber mit einem DAX, der viele Kritiker Lügen gestraft hat. Über 21 Prozent Kursplus seit Jahresbeginn, stärker als der US-Markt. Wer hätte das noch vor Monaten erwartet?

Genau solche Entwicklungen machen den Reiz der Börse aus. Denn auch 2026 dürfte wieder alles anders kommen als gedacht. Während viele Analysten weiter steigende Kurse erwarten, rückt eine zentrale Frage in den Fokus: Wo entstehen im kommenden Jahr echte Überraschungen, und wie kann man davon profitieren?

Unser aktueller Spezialreport beleuchtet fünf Entwicklungen, mit denen kaum jemand rechnet, die aber enormes Renditepotenzial bergen. Vom Comeback der Ölwerte über unterschätzte Plattform-Aktien bis hin zur möglichen Wachablösung im KI-Sektor: Wer 2026 überdurchschnittlich abschneiden will, muss antizyklisch denken und frühzeitig Position beziehen.

Im kostenlosen Report stellen wir 5 Aktien vor, die 2026 im Zentrum solcher Wendepunkte stehen könnten. Solide bewertet, gut positioniert und mit überraschend starkem Momentum.

Jetzt kostenlos herunterladen! Bevor andere erkennen, wo die Chancen wirklich liegen!

Dieses exklusive PDF ist nur für kurze Zeit verfügbar.
Werbehinweise: Die Billigung des Basisprospekts durch die BaFin ist nicht als ihre Befürwortung der angebotenen Wertpapiere zu verstehen. Wir empfehlen Interessenten und potenziellen Anlegern den Basisprospekt und die Endgültigen Bedingungen zu lesen, bevor sie eine Anlageentscheidung treffen, um sich möglichst umfassend zu informieren, insbesondere über die potenziellen Risiken und Chancen des Wertpapiers. Sie sind im Begriff, ein Produkt zu erwerben, das nicht einfach ist und schwer zu verstehen sein kann.