Iraq's Ministry of Electricity says an initial 61 MW from the first unit of a planned 1 GW solar project has commenced. The project is being developed across four 250 MW units, with final commissioning currently scheduled for 2028.Trial operation of the first generating unit of Iraq's 1 GW Basra solar power plant is underway. An update from the Iraqi Ministry of Electricity explains 61 MW from the first of four 250 MW units has begun operating. It adds that loads will be increased sequentially until the first unit reaches its full 250 MW capacity, at which point the plant will be connected to ...Den vollständigen Artikel lesen ...