June 10 (Reuters) - Williams Partners LP:
* L.P. provides second update on Ignacio gas processing plant
* Says incident will reduce second-quarter 2009 cash flows by approximately $5
million to $6 million
* Says now believes that work to ensure safe and reliable operations will be
completed late next week
* Says estimated repair costs of approximately $1.6 million
* Says does not expect incident to affect distributions or have material impact
on financial position
((Bangalore Equities Newsroom; +91 80 4135 5800; within U.S. +1 646 223 8780))
(For more news, please click here) COPYRIGHT Copyright Thomson Reuters 2009. All rights reserved. The copying, republication or redistribution of Reuters News Content, including by framing or similar means, is expressly prohibited without the prior written consent of Thomson Reuters.
* L.P. provides second update on Ignacio gas processing plant
* Says incident will reduce second-quarter 2009 cash flows by approximately $5
million to $6 million
* Says now believes that work to ensure safe and reliable operations will be
completed late next week
* Says estimated repair costs of approximately $1.6 million
* Says does not expect incident to affect distributions or have material impact
on financial position
((Bangalore Equities Newsroom; +91 80 4135 5800; within U.S. +1 646 223 8780))
(For more news, please click here) COPYRIGHT Copyright Thomson Reuters 2009. All rights reserved. The copying, republication or redistribution of Reuters News Content, including by framing or similar means, is expressly prohibited without the prior written consent of Thomson Reuters.