WASHINGTON, March 19 (Reuters) - The estimated total cost of Lockheed Martin Corp's F-35 fighter jets being bought by the Pentagon may be nearly twice as high as originally forecast, the U.S. Defense Department said Friday.
The bill for 2,443 F-35s is currently estimated at $278 billion to $329 billion, up from the $197 billion projected when the development program began in October 2001, taking into account inflation, a one-page Pentagon F-35 'unit cost' report said.
The percentage hike per aircraft is even higher than for the fleet overall because the Pentagon now plans to buy 409 fewer F-35s than the 2,852 it originally planned.
The single-seat, single-engine F-35 is built to evade detection by radar. Also known as the Joint Strike Fighter, it is the Pentagon's costliest arms procurement program.
Three highly common models are being built for the U.S. Air Force, Marine Corps and Navy as well as eight international partners and other prospective foreign buyers.
Defense Secretary Robert Gates fired the Pentagon's F-35 program manager in February. He also added 13 months and $2.8 billion to the development phase plus four more test aircraft.
The Government Accountability Office, in a report to Congress Friday, said the latest Pentagon steps should 'improve outcomes and provide more realistic cost and schedule estimates.'
But further cost growth and schedule extensions are likely, the Congress's non-partisan audit and investigative arm said.
Lockheed Martin, the Pentagon's No. 1 contractor by sales, had no immediate comment. Keywords: LOCKHEED FIGHTER (Reporting by Jim Wolf, editing by Bernard Orr; Reuters Messaging: jim.wolf.reuters.com@reuters.net; email: jim.wolf@thomsonreuters.com; +1 202 898 8402, fax +1 202 310 5490) COPYRIGHT Copyright Thomson Reuters 2010. All rights reserved. The copying, republication or redistribution of Reuters News Content, including by framing or similar means, is expressly prohibited without the prior written consent of Thomson Reuters.
WASHINGTON, March 19 (Reuters) - The estimated total cost of Lockheed Martin Corp's F-35 fighter jets being bought by the Pentagon may be nearly twice as high as originally forecast, the U.S. Defense Department said Friday.
The bill for 2,443 F-35s is currently estimated at $278 billion to $329 billion, up from the $197 billion projected when the development program began in October 2001, taking into account inflation, a one-page Pentagon F-35 'unit cost' report said.
The percentage hike per aircraft is even higher than for the fleet overall because the Pentagon now plans to buy 409 fewer F-35s than the 2,852 it originally planned.
The single-seat, single-engine F-35 is built to evade detection by radar. Also known as the Joint Strike Fighter, it is the Pentagon's costliest arms procurement program.
Three highly common models are being built for the U.S. Air Force, Marine Corps and Navy as well as eight international partners and other prospective foreign buyers.
Defense Secretary Robert Gates fired the Pentagon's F-35 program manager in February. He also added 13 months and $2.8 billion to the development phase plus four more test aircraft.
The Government Accountability Office, in a report to Congress Friday, said the latest Pentagon steps should 'improve outcomes and provide more realistic cost and schedule estimates.'
But further cost growth and schedule extensions are likely, the Congress's non-partisan audit and investigative arm said.
Lockheed Martin, the Pentagon's No. 1 contractor by sales, had no immediate comment. Keywords: LOCKHEED FIGHTER (Reporting by Jim Wolf, editing by Bernard Orr; Reuters Messaging: jim.wolf.reuters.com@reuters.net; email: jim.wolf@thomsonreuters.com; +1 202 898 8402, fax +1 202 310 5490) COPYRIGHT Copyright Thomson Reuters 2010. All rights reserved. The copying, republication or redistribution of Reuters News Content, including by framing or similar means, is expressly prohibited without the prior written consent of Thomson Reuters.