Anzeige
Mehr »
Mittwoch, 11.03.2026 - Börsentäglich über 12.000 News
Das Triple-Discovery-Setup, das der Markt noch nicht begriffen hat!!
Anzeige

Indizes

Kurs

%
News
24 h / 7 T
Aufrufe
7 Tage

Aktien

Kurs

%
News
24 h / 7 T
Aufrufe
7 Tage

Xetra-Orderbuch

Fonds

Kurs

%

Devisen

Kurs

%

Rohstoffe

Kurs

%

Themen

Kurs

%

Erweiterte Suche

WKN: A2ALV4 | ISIN: CA1671012039 | Ticker-Symbol: CLL1
München
10.03.26 | 08:03
0,150 Euro
0,00 % 0,000
Branche
Rohstoffe
Aktienmarkt
Sonstige
1-Jahres-Chart
CHIBOUGAMAU INDEPENDENT MINES INC Chart 1 Jahr
5-Tage-Chart
CHIBOUGAMAU INDEPENDENT MINES INC 5-Tage-Chart
RealtimeGeldBriefZeit
0,1510,18810.03.
GlobeNewswire (Europe)
216 Leser
Artikel bewerten:
(1)

Chibougamau Independent Mines Inc.: Cerrado States that Mont Sorcier Feasibility Contemplates a Higher Through-put Rate by 60%

TORONTO, Nov. 12, 2025 (GLOBE NEWSWIRE) -- Chibougamau Independent Mines Inc. (CBG-TSX-V in Canada, CLL1-Frankfurt, Stuttgart, Berlin and Lang & Schwarz Stock Exchanges in Germany, CMAUF-OTC in the US), herein called Chibougamau, is pleased to inform shareholders that Cerrado Gold Inc. has provided an update on the progress to the development of its Mont Sorcier high purity magnetite iron project located on the traditional Cree Territory of Eeyou Istche James Bay in the municipality of Chibougamau, Quebec. The Mont Sorcier project is currently in the later stages of a feasibility study which Cerrado has targeted to be completed by Q2/2026. Chibougamau holds a 2% Gross Metal Royalty (GMR) on Iron and Vanadium production from the Mont Sorcier Project.

The Key Updates to the Mont Sorcier Feasibility Study

  • Cerrado stated that the feasibility study will contemplate a 60% increase in the production rate to 8 million tonnes per annum vs. 5 million tonnes per annum in the PEA published September 8, 2022.
  • Cerrado has indicated that a phased production start from 4 million tonnes per annum at the start to 8 million tonnes per annum in approximately the 3rd year of production. This increase is forecasted to increase capital costs for phase one by 30-40% relative to the PEA due to revised flow sheet design and infrastructure upsizing to meet the eventual phase two throughput. Cerrado expects Phase 2 capital costs to be significantly lower due in part to the construction of certain facilities in phase one which were previously planned to be constructed in phase two.
  • Cerrado stated that the resource will see an additional 17,890 metres of resource definition drilling added to the database, with some assays still pending.
  • Cerrado anticipates the mine life will remain at 20 years despite the increase in through-put due to the expected results of the next mineral resource update.
  • Cerrado indicated that the Mont Sorcier project is progressing well to submit the projects ESIA in Q4/2026 and are still confident that construction could start in mid 2028, if all permits and financing requirements are received.

Chibougamau is pleased to see Cerrado's continued progress of the Mont Sorcier project feasibility study towards production.

Shareholders seeking more detailed information are advised to access the Cerrado Gold Inc. press release dated November 10, 2025 by clicking here.

This press release was written by David Christie, P. Geo., Consultant for Chibougamau Independent Mines Ind. in his capacity as a Qualified Person (Q.P.) under NI 43-101.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this news release.



We Seek Safe Harbour.
CUSIP Number 167101 203
LEI 529900GYUP9EBEF7U709


For further information, contact:
Jack Stoch, P.Geo., Acc.Dir.
President & CEO
Chibougamau Independent Mines Inc.
86, 14th Street
Rouyn-Noranda, Quebec Canada J9X 2J1

Tel.: 819.797.5242
Fax: 819.797.1470
info@chibougamaumines.com
www.chibougamaumines.com

Forward Looking Statements

Except for historical information this News Release may contain certain "forward looking statements". These statements may involve a number of known and unknown risks and uncertainties and other factors that may cause the actual results, level of activity and performance to be materially different from the Companies expectations and projections. A more detailed discussion of the risks is available under "disclaimer" on the Company's website.


© 2025 GlobeNewswire (Europe)
Tech-Aktien schwanken – 3 Versorger mit Rückenwind
Die Stimmung an den Märkten hat sich grundlegend gedreht. Während Tech- und KI-Werte zunehmend mit Volatilität und Bewertungsrisiken kämpfen, erleben klassische Versorger ein unerwartetes Comeback. Laut IEA und EIA steigt der globale Strombedarf strukturell weiter, nicht nur wegen E-Mobilität und Wärmepumpen, sondern vor allem durch energiehungrige KI-Rechenzentren. Energie wird damit zur zentralen Infrastruktur des digitalen Zeitalters.

Gleichzeitig rücken in unsicheren Marktphasen stabile Cashflows, solide Bilanzen und regulierte Renditen wieder stärker in den Fokus. Genau hier spielen Versorger ihre Stärken aus: berechenbare Erträge, robuste Nachfrage und hohe Dividenden – Qualitäten, die vielen Wachstumswerten aktuell fehlen.

Nach Jahren im Schatten der Tech-Rallye steigt nun das Interesse an Unternehmen, die Stabilität mit langfristigen Wachstumsthemen wie Netzausbau, Dekarbonisierung und erneuerbaren Energien verbinden.

Im aktuellen Spezialreport stellen wir drei Versorger vor, die defensive Stärke mit attraktivem Potenzial kombinieren.

Jetzt den kostenlosen Report sichern – bevor die nächste Versorgerwelle Fahrt aufnimmt!
Werbehinweise: Die Billigung des Basisprospekts durch die BaFin ist nicht als ihre Befürwortung der angebotenen Wertpapiere zu verstehen. Wir empfehlen Interessenten und potenziellen Anlegern den Basisprospekt und die Endgültigen Bedingungen zu lesen, bevor sie eine Anlageentscheidung treffen, um sich möglichst umfassend zu informieren, insbesondere über die potenziellen Risiken und Chancen des Wertpapiers. Sie sind im Begriff, ein Produkt zu erwerben, das nicht einfach ist und schwer zu verstehen sein kann.